17402-17406 W DEVONSHIRE ST 91325
Certificate Information: 17402-17406 W DEVONSHIRE ST 91325
- Application / Permit
- 22014-20000-02099
- Plan Check / Job No.
- B22VN06674
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- GROUND FLOOR ADDITION TO (E) SFD, convert attached garage into JADU and second story addition ATTACHED ADU PER ORDINANCE. The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.
- Permit Issued
- Issued on 11/11/2022
- Issuing Office
- Current Status
- CofO Issued on 9/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/19/2022 | CARLOS MONTES |
| Corrections Issued | 5/21/2022 | CARLOS MONTES |
| Quality Review Completed | 6/8/2022 | MICHAEL PEREZ |
| Plan Check Approved | 11/9/2022 | CARLOS MONTES |
| Issued | 11/11/2022 | APPLICANT |
| CofO in Progress | 8/4/2023 | JAVIER RAMOS JR |
| CofO Issued | 9/11/2023 | RUBEN SALAS |
| Permit Finaled | 9/11/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Miscellaneous | Cleared | 5/26/2022 | MIGUEL GAMBOA |
| Roof/Waste drainage to street | Cleared | 6/7/2022 | DAGOVERTO GUERRERO |
| Address approval | Cleared | 6/9/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 6/10/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 6/10/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Trinity Builders & Design Inc; Lic. No.: 988119-B | , |
| Engineer | Wassef,, Mena; Lic. No.: C84979 | 28131 VALERIO CT VALENCIA, CA 91354 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/9/2023 | Conditional Approval | MICHAEL SMITH |
| Footing/Foundation/Slab | 2/13/2023 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 2/13/2023 | Partial Approval | JAVIER RAMOS JR |
| Deputy Drilled-In Anchors | 2/21/2023 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 2/21/2023 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2023 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2023 | Partial Approval | JAVIER RAMOS JR |
| Deputy Wood Construction | 3/28/2023 | Conditional Approval | MICHAEL SMITH |
| BUILDING-Rough-Frame | 4/21/2023 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 4/21/2023 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2023 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 4/21/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 4/21/2023 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 4/21/2023 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 4/21/2023 | Approved | JAVIER RAMOS JR |
| Insulation | 5/2/2023 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 5/2/2023 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 5/8/2023 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 6/27/2023 | Corrections Issued | JAVIER RAMOS JR |
| HVAC-Final | 6/27/2023 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 6/27/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Final | 7/10/2023 | Approved | JAVIER RAMOS JR |
| Final | 7/10/2023 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 7/10/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| PLUMBING-Final | 7/10/2023 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 7/10/2023 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 7/10/2023 | Approved | JAVIER RAMOS JR |
| Final | 8/4/2023 | OK to Issue CofO | JAVIER RAMOS JR |
| Green Building Final | 8/4/2023 | Approved | JAVIER RAMOS JR |
| Service/Power Release | 8/4/2023 | Approved | JAVIER RAMOS JR |