2725 S OAKHURST AVE 90034

Certificate Information: 2725 S OAKHURST AVE 90034

Application / Permit
22014-20000-02087
Plan Check / Job No.
B22VN06635
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
7'-3" X 25'-11" ADDITION TO THE FRONT AND A 24' X 9'-11" ADDITION TO THE REAR OF THE (E) SFD.
Permit Issued
Issued on 1/17/2023
Issuing Office
Valley
Current Status
CofO Issued on 4/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/2/2022 APPLICANT
Assigned to Plan Check Engineer 5/6/2022 SERGIO MUNIZ
Corrections Issued 5/7/2022 SERGIO MUNIZ
Applicant returned to address corrections 6/23/2022 SERGIO MUNIZ
Applicant returned to address corrections 7/2/2022 SERGIO MUNIZ
Plan Check Approved 7/8/2022 SERGIO MUNIZ
Building Plans Picked Up 7/11/2022 APPLICANT
Issued 1/17/2023 APPLICANT
CofO in Progress 4/1/2024 OGANES TARAKHCHYAN
Permit Finaled 4/3/2024 DANIEL ORRANTE
CofO Issued 4/3/2024 DANIEL ORRANTE
Permit Finaled 4/3/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/3/2022 ROMAN GUTIERREZ
Roof/Waste drainage to street Cleared 6/3/2022 ROMAN GUTIERREZ
Sewer availability Cleared 6/3/2022 ROMAN GUTIERREZ
Public Works-Highway Ded. Cleared 6/3/2022 ROMAN GUTIERREZ
Public Works-Open Permits Cleared 6/3/2022 ROMAN GUTIERREZ
Public Works-Sewers Cleared 6/3/2022 ROMAN GUTIERREZ
Grading Pre-Inspection Cleared 6/6/2022 MANUEL TEJADA

Contact Information

Contractor Ground Up Builders; Lic. No.: 911849-B 14545 VICTORY BLVD STE 601      VAN NUYS, CA 91411
Engineer Wu,, Harold Ping-Hung; Lic. No.: C35693 1168 SAN GABRIEL BLVD NO N      ROSEMEAD, CA 91770

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/9/2023 Conditional Approval DAVID FEILER
Footing/Foundation/Slab 2/14/2023 Corrections Issued ASHLEY THOMPSON
METHANE-Barrier 2/14/2023 Approved ASHLEY THOMPSON
METHANE-Subgrade 2/14/2023 Approved ASHLEY THOMPSON
Footing/Foundation/Slab 2/22/2023 Approved ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 3/2/2023 Partial Approval ASHLEY THOMPSON
Green Building Rough 3/2/2023 Not Ready for Inspection ASHLEY THOMPSON
METHANE-Rough 3/2/2023 Approved ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 3/7/2023 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 3/29/2023 Partial Inspection JEREMY TODD
PLUMBING-Rough 4/12/2023 Partial Approval JEREMY TODD
PLUMBING-Rough 4/26/2023 Approved JEREMY TODD
BUILDING-Rough-Frame 5/17/2023 Not Ready for Inspection CLAYTON GRAHAM
ELECTRICAL-Rough 5/17/2023 Corrections Issued CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 5/17/2023 Partial Approval CLAYTON GRAHAM
Green Building Rough 5/17/2023 Not Ready for Inspection CLAYTON GRAHAM
ELECTRICAL-Rough 5/22/2023 Approved CLAYTON GRAHAM
BUILDING-Rough-Frame 6/1/2023 Corrections Issued CLAYTON GRAHAM
Green Building Rough 6/1/2023 Not Ready for Inspection CLAYTON GRAHAM
Wood Frame 6/1/2023 Not Ready for Inspection CLAYTON GRAHAM
HVAC-Rough 6/5/2023 Approved JEREMY TODD
Interior/Exterior Lathing 6/5/2023 Approved JEREMY TODD
BUILDING-Rough-Frame 7/5/2023 Corrections Issued CLAYTON GRAHAM
Green Building Rough 7/5/2023 Corrections Issued CLAYTON GRAHAM
Insulation 7/5/2023 Not Ready for Inspection CLAYTON GRAHAM
BUILDING-Rough-Frame 7/19/2023 Approved CLAYTON GRAHAM
Green Building Rough 7/19/2023 Approved CLAYTON GRAHAM
Insulation 7/19/2023 Corrections Issued CLAYTON GRAHAM
Insulation 8/9/2023 Approved CLAYTON GRAHAM
Drywall Nailing 9/6/2023 Approved BEN MOLSTAD
Shower Pan 9/26/2023 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 10/3/2023 Approved BEN MOLSTAD
ELECTRICAL-Final 11/3/2023 Partial Approval MEL KHACHATOURIAN
Final 1/24/2024 Corrections Issued OGANES TARAKHCHYAN
Green Building Final 1/24/2024 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 1/24/2024 SGSOV Not Ready OGANES TARAKHCHYAN
Smoke Detectors 1/24/2024 Approved OGANES TARAKHCHYAN
Final 2/14/2024 Corrections Issued OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 2/14/2024 SGSOV Approved OGANES TARAKHCHYAN
Final 3/29/2024 OK to Issue CofO OGANES TARAKHCHYAN