2725 S OAKHURST AVE 90034
Certificate Information: 2725 S OAKHURST AVE 90034
- Application / Permit
- 22014-20000-02087
- Plan Check / Job No.
- B22VN06635
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 7'-3" X 25'-11" ADDITION TO THE FRONT AND A 24' X 9'-11" ADDITION TO THE REAR OF THE (E) SFD.
- Permit Issued
- Issued on 1/17/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2022 | SERGIO MUNIZ |
| Corrections Issued | 5/7/2022 | SERGIO MUNIZ |
| Applicant returned to address corrections | 6/23/2022 | SERGIO MUNIZ |
| Applicant returned to address corrections | 7/2/2022 | SERGIO MUNIZ |
| Plan Check Approved | 7/8/2022 | SERGIO MUNIZ |
| Building Plans Picked Up | 7/11/2022 | APPLICANT |
| Issued | 1/17/2023 | APPLICANT |
| CofO in Progress | 4/1/2024 | OGANES TARAKHCHYAN |
| Permit Finaled | 4/3/2024 | DANIEL ORRANTE |
| CofO Issued | 4/3/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/3/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/3/2022 | ROMAN GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 6/3/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 6/3/2022 | ROMAN GUTIERREZ |
| Public Works-Highway Ded. | Cleared | 6/3/2022 | ROMAN GUTIERREZ |
| Public Works-Open Permits | Cleared | 6/3/2022 | ROMAN GUTIERREZ |
| Public Works-Sewers | Cleared | 6/3/2022 | ROMAN GUTIERREZ |
| Grading Pre-Inspection | Cleared | 6/6/2022 | MANUEL TEJADA |
Contact Information
| Contractor | Ground Up Builders; Lic. No.: 911849-B | 14545 VICTORY BLVD STE 601 VAN NUYS, CA 91411 |
| Engineer | Wu,, Harold Ping-Hung; Lic. No.: C35693 | 1168 SAN GABRIEL BLVD NO N ROSEMEAD, CA 91770 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/9/2023 | Conditional Approval | DAVID FEILER |
| Footing/Foundation/Slab | 2/14/2023 | Corrections Issued | ASHLEY THOMPSON |
| METHANE-Barrier | 2/14/2023 | Approved | ASHLEY THOMPSON |
| METHANE-Subgrade | 2/14/2023 | Approved | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 2/22/2023 | Approved | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2023 | Partial Approval | ASHLEY THOMPSON |
| Green Building Rough | 3/2/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| METHANE-Rough | 3/2/2023 | Approved | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2023 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2023 | Partial Inspection | JEREMY TODD |
| PLUMBING-Rough | 4/12/2023 | Partial Approval | JEREMY TODD |
| PLUMBING-Rough | 4/26/2023 | Approved | JEREMY TODD |
| BUILDING-Rough-Frame | 5/17/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 5/17/2023 | Corrections Issued | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2023 | Partial Approval | CLAYTON GRAHAM |
| Green Building Rough | 5/17/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 5/22/2023 | Approved | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 6/1/2023 | Corrections Issued | CLAYTON GRAHAM |
| Green Building Rough | 6/1/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Wood Frame | 6/1/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| HVAC-Rough | 6/5/2023 | Approved | JEREMY TODD |
| Interior/Exterior Lathing | 6/5/2023 | Approved | JEREMY TODD |
| BUILDING-Rough-Frame | 7/5/2023 | Corrections Issued | CLAYTON GRAHAM |
| Green Building Rough | 7/5/2023 | Corrections Issued | CLAYTON GRAHAM |
| Insulation | 7/5/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 7/19/2023 | Approved | CLAYTON GRAHAM |
| Green Building Rough | 7/19/2023 | Approved | CLAYTON GRAHAM |
| Insulation | 7/19/2023 | Corrections Issued | CLAYTON GRAHAM |
| Insulation | 8/9/2023 | Approved | CLAYTON GRAHAM |
| Drywall Nailing | 9/6/2023 | Approved | BEN MOLSTAD |
| Shower Pan | 9/26/2023 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 10/3/2023 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 11/3/2023 | Partial Approval | MEL KHACHATOURIAN |
| Final | 1/24/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Green Building Final | 1/24/2024 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 1/24/2024 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 1/24/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 2/14/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 2/14/2024 | SGSOV Approved | OGANES TARAKHCHYAN |
| Final | 3/29/2024 | OK to Issue CofO | OGANES TARAKHCHYAN |