18419 W SYLVAN ST 91335

Certificate Information: 18419 W SYLVAN ST 91335

Application / Permit
22014-20000-02061
Plan Check / Job No.
B22VN06535
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: (N) ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING.
Permit Issued
Issued on 7/10/2024
Issuing Office
Current Status
Issued on 7/10/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/4/2022 APPLICANT
Assigned to Plan Check Engineer 5/5/2022 DANIEL YIP
Corrections Issued 5/6/2022 DANIEL YIP
Plan Check Approved 6/10/2022 DANIEL YIP
No Progress 6/29/2022 DANIEL YIP
Plan Check Approved 6/29/2022 DANIEL YIP
Issued 7/10/2024 APPLICANT

Permit Application Clearance Information

ZI Cleared 5/26/2022 STEVEN WECHSLER
Roof/Waste drainage to street Cleared 6/1/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 6/7/2022 DAGOVERTO GUERRERO

Contact Information

Contractor American Home Improvement Inc; Lic. No.: 835537-B 20335 VENTURA BLVD #422      WOODLAND HILLS, CA 91364
Engineer Singh,, Jasbir; Lic. No.: C38767 16194 EASTRIDGE CT      CHINO HILLS, CA 91709

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/29/2024 Corrections Issued MORRIS JACKSON
Footing/Foundation/Slab 9/9/2024 Corrections Issued MORRIS JACKSON
Footing/Foundation/Slab 9/16/2024 Approved MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 9/25/2024 Partial Approval MORRIS JACKSON
PLUMBING-Rough 9/25/2024 Approved MORRIS JACKSON
Underground Mechanical 9/25/2024 Approved MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 10/2/2024 Partial Approval JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 10/9/2024 Partial Approval MORRIS JACKSON
Deputy Drilled-In Anchors 10/11/2024 Conditional Approval MORRIS JACKSON
BUILDING-Rough-Frame 10/22/2024 Partial Approval JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 10/22/2024 Approved JON MCHUGH
Green Building Rough 10/22/2024 Not Ready for Inspection JON MCHUGH
Rough-Elec/Plmb/HVAC 10/22/2024 Approved JON MCHUGH
BUILDING-Rough-Frame 11/5/2024 Approved MORRIS JACKSON
Green Building Rough 11/5/2024 Approved MORRIS JACKSON
Insulation 11/5/2024 Approved MORRIS JACKSON
Interior/Exterior Lathing 11/5/2024 Partial Approval MORRIS JACKSON
Shower Pan 11/5/2024 Approved MORRIS JACKSON
Drywall Nailing 11/8/2024 Approved MORRIS JACKSON
Interior/Exterior Lathing 11/8/2024 Approved MORRIS JACKSON
Final 1/21/2025 Corrections Issued MORRIS JACKSON
Green Building Final 1/21/2025 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 1/21/2025 SGSOV Approved MORRIS JACKSON
Smoke Detectors 1/21/2025 Approved MORRIS JACKSON