3220 S KELTON AVE 90034

Certificate Information: 3220 S KELTON AVE 90034

Application / Permit
22014-20000-02043
Plan Check / Job No.
B22VN06497
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE MOST (E) INT. AND EXT WALLS EXCEPT FOR SOME SIDE EXT. WALLS AND ERECT A 40'-4" x 52'-11" TWO STORY SINGLE FAMILY DWELLING W/ ATT. 2-CAR GARAGE AND ATT. WOOD DECK; NFPA-13D THRU-OUT
Permit Issued
Issued on 11/18/2022
Issuing Office
Metro
Current Status
CofO Issued on 11/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/25/2022 APPLICANT
Assigned to Plan Check Engineer 6/2/2022 SEAN SHAHMIRI
Corrections Issued 6/6/2022 SEAN SHAHMIRI
Quality Review Completed 6/10/2022 OMID HEDAYAT
Building Plans Picked Up 6/13/2022 APPLICANT
Applicant returned to address corrections 9/22/2022 SEAN SHAHMIRI
Plan Check Approved 10/17/2022 SEAN SHAHMIRI
Issued 11/18/2022 APPLICANT
CofO in Progress 11/7/2025 DAVID FEILER
Permit Finaled 11/7/2025 RICHARD STEINBACH
CofO Issued 11/7/2025 RICHARD STEINBACH
Permit Finaled 11/7/2025 RICHARD STEINBACH

Permit Application Clearance Information

Specific Plan Cleared 6/8/2022 MIGUEL GAMBOA
ZA Case Cleared 6/8/2022 MIGUEL GAMBOA
Address approval Cleared 6/11/2022 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 6/13/2022 SAUL GARCIA
Sewer availability Cleared 6/13/2022 SAUL GARCIA
Grading Pre-Inspection Cleared 6/16/2022 KIRK LINKLATER
Specific Plan Cleared 6/22/2022 FREDDY GARCIA
Low Impact Development Cleared 7/13/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 7/18/2022 SAUL GARCIA

Contact Information

Architect Chiedu, Chukwuma; Lic. No.: C33595       ,
Contractor D U A Build; Lic. No.: 967782-B 3579 EAST FOOTHILL BLVD #405      PASADENA, CA 91107

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/4/2023 Not Ready for Inspection JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 5/9/2023 Partial Approval JOHNNY MIRANDA
Footing/Foundation/Slab 6/8/2023 Conditional Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 9/26/2023 Corrections Issued JESUS PINEDA
BUILDING-Rough-Frame 11/14/2023 Corrections Issued MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 11/14/2023 Partial Inspection JESUS PINEDA
Special/Order Compliance 11/14/2023 Corrections Issued MICHAEL PELHAM
Special/Order Compliance 11/15/2023 Corrections Issued MICHAEL PELHAM
ELECTRICAL-Rough 1/22/2024 Corrections Issued JESUS PINEDA
HVAC-Rough 1/22/2024 Conditional Approval JESUS PINEDA
PLUMBING-Rough 1/22/2024 Corrections Issued JESUS PINEDA
ELECTRICAL-Rough 1/31/2024 Conditional Approval JESUS PINEDA
PLUMBING-Rough 1/31/2024 Conditional Approval JESUS PINEDA
BUILDING-Rough-Frame 2/21/2024 Approved JESUS PINEDA
ELECTRICAL-Rough 2/21/2024 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 2/21/2024 Approved JESUS PINEDA
Footing/Foundation/Slab 2/21/2024 Approved JESUS PINEDA
Green Building Rough 2/21/2024 Approved JESUS PINEDA
HVAC-Rough 2/21/2024 Approved JESUS PINEDA
Insulation 2/21/2024 Corrections Issued JESUS PINEDA
Interior/Exterior Lathing 2/21/2024 Partial Approval JESUS PINEDA
PLUMBING-Rough 2/21/2024 Approved JESUS PINEDA
Verify Sprinkler Sign Off 2/21/2024 Approved JESUS PINEDA
Interior/Exterior Lathing 2/26/2024 Corrections Issued JESUS PINEDA
Shower Pan 2/26/2024 Approved JESUS PINEDA
Drywall Nailing 3/4/2024 Not Ready for Inspection JESUS PINEDA
Interior/Exterior Lathing 3/4/2024 Partial Approval JESUS PINEDA
Drywall Nailing 3/7/2024 Approved HERBERT GIRON
Service/Power Release 4/19/2024 Corrections Issued JESUS PINEDA
Service/Power Release 4/23/2024 Approved JESUS PINEDA
ELECTRICAL-Final 5/30/2025 Approved WILBER ROSALES
Final 5/30/2025 Corrections Issued WILBER ROSALES
Green Building Final 5/30/2025 Approved WILBER ROSALES
HVAC-Final 5/30/2025 Approved WILBER ROSALES
PLUMBING-Final 5/30/2025 Approved WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 5/30/2025 SGSOV Approved WILBER ROSALES
Smoke Detectors 5/30/2025 Approved WILBER ROSALES
Final 11/7/2025 OK to Issue CofO DAVID FEILER