3220 S KELTON AVE 90034
Certificate Information: 3220 S KELTON AVE 90034
- Application / Permit
- 22014-20000-02043
- Plan Check / Job No.
- B22VN06497
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE MOST (E) INT. AND EXT WALLS EXCEPT FOR SOME SIDE EXT. WALLS AND ERECT A 40'-4" x 52'-11" TWO STORY SINGLE FAMILY DWELLING W/ ATT. 2-CAR GARAGE AND ATT. WOOD DECK; NFPA-13D THRU-OUT
- Permit Issued
- Issued on 11/18/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2022 | SEAN SHAHMIRI |
| Corrections Issued | 6/6/2022 | SEAN SHAHMIRI |
| Quality Review Completed | 6/10/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 6/13/2022 | APPLICANT |
| Applicant returned to address corrections | 9/22/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 10/17/2022 | SEAN SHAHMIRI |
| Issued | 11/18/2022 | APPLICANT |
| CofO in Progress | 11/7/2025 | DAVID FEILER |
| Permit Finaled | 11/7/2025 | RICHARD STEINBACH |
| CofO Issued | 11/7/2025 | RICHARD STEINBACH |
| Permit Finaled | 11/7/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Specific Plan | Cleared | 6/8/2022 | MIGUEL GAMBOA |
| ZA Case | Cleared | 6/8/2022 | MIGUEL GAMBOA |
| Address approval | Cleared | 6/11/2022 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2022 | SAUL GARCIA |
| Sewer availability | Cleared | 6/13/2022 | SAUL GARCIA |
| Grading Pre-Inspection | Cleared | 6/16/2022 | KIRK LINKLATER |
| Specific Plan | Cleared | 6/22/2022 | FREDDY GARCIA |
| Low Impact Development | Cleared | 7/13/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 7/18/2022 | SAUL GARCIA |
Contact Information
| Architect | Chiedu, Chukwuma; Lic. No.: C33595 | , |
| Contractor | D U A Build; Lic. No.: 967782-B | 3579 EAST FOOTHILL BLVD #405 PASADENA, CA 91107 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/4/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 5/9/2023 | Partial Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 6/8/2023 | Conditional Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2023 | Corrections Issued | JESUS PINEDA |
| BUILDING-Rough-Frame | 11/14/2023 | Corrections Issued | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2023 | Partial Inspection | JESUS PINEDA |
| Special/Order Compliance | 11/14/2023 | Corrections Issued | MICHAEL PELHAM |
| Special/Order Compliance | 11/15/2023 | Corrections Issued | MICHAEL PELHAM |
| ELECTRICAL-Rough | 1/22/2024 | Corrections Issued | JESUS PINEDA |
| HVAC-Rough | 1/22/2024 | Conditional Approval | JESUS PINEDA |
| PLUMBING-Rough | 1/22/2024 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 1/31/2024 | Conditional Approval | JESUS PINEDA |
| PLUMBING-Rough | 1/31/2024 | Conditional Approval | JESUS PINEDA |
| BUILDING-Rough-Frame | 2/21/2024 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 2/21/2024 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2024 | Approved | JESUS PINEDA |
| Footing/Foundation/Slab | 2/21/2024 | Approved | JESUS PINEDA |
| Green Building Rough | 2/21/2024 | Approved | JESUS PINEDA |
| HVAC-Rough | 2/21/2024 | Approved | JESUS PINEDA |
| Insulation | 2/21/2024 | Corrections Issued | JESUS PINEDA |
| Interior/Exterior Lathing | 2/21/2024 | Partial Approval | JESUS PINEDA |
| PLUMBING-Rough | 2/21/2024 | Approved | JESUS PINEDA |
| Verify Sprinkler Sign Off | 2/21/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 2/26/2024 | Corrections Issued | JESUS PINEDA |
| Shower Pan | 2/26/2024 | Approved | JESUS PINEDA |
| Drywall Nailing | 3/4/2024 | Not Ready for Inspection | JESUS PINEDA |
| Interior/Exterior Lathing | 3/4/2024 | Partial Approval | JESUS PINEDA |
| Drywall Nailing | 3/7/2024 | Approved | HERBERT GIRON |
| Service/Power Release | 4/19/2024 | Corrections Issued | JESUS PINEDA |
| Service/Power Release | 4/23/2024 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 5/30/2025 | Approved | WILBER ROSALES |
| Final | 5/30/2025 | Corrections Issued | WILBER ROSALES |
| Green Building Final | 5/30/2025 | Approved | WILBER ROSALES |
| HVAC-Final | 5/30/2025 | Approved | WILBER ROSALES |
| PLUMBING-Final | 5/30/2025 | Approved | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 5/30/2025 | SGSOV Approved | WILBER ROSALES |
| Smoke Detectors | 5/30/2025 | Approved | WILBER ROSALES |
| Final | 11/7/2025 | OK to Issue CofO | DAVID FEILER |