16830 W ADLON ROAD 91436

Certificate Information: 16830 W ADLON ROAD 91436

Application / Permit
22014-20000-02040
Plan Check / Job No.
B22VN06491
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1-STORY ADDT'N (IRR 36'- 2 1/2" X 19'-2") TO REAR OF (E) 1-STORY SFD W/ ATTACHED GARAGE: ADD (N) ATTIC AREA (6' X 8'); ADD BATHROOM & EXPAND ENTRY AT FRONT (19' X 4'); INTERIOR REMODEL
Permit Issued
Issued on 8/18/2022
Issuing Office
Metro
Current Status
CofO Issued on 3/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/27/2022 APPLICANT
Assigned to Plan Check Engineer 5/19/2022 COLIN LOREDO
Corrections Issued 5/24/2022 COLIN LOREDO
Quality Review Completed 5/25/2022 OMID HEDAYAT
Building Plans Picked Up 5/31/2022 APPLICANT
Plan Check Approved 8/16/2022 NILOOFAR MEHRAIN
Issued 8/18/2022 APPLICANT
CofO in Progress 1/10/2025 JOHN COLEMAN
CofO in Progress 3/19/2025 SEAN WIRCH
Permit Finaled 3/28/2025 JOHN JANSON
CofO Issued 3/28/2025 JOHN JANSON
Permit Finaled 3/28/2025 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/26/2022 CHRIS CHAHBAZ
Hydrant and Access approval Cleared 6/10/2022 KURT CORRAL
Eng Process Fee Ord 176,300 Cleared 7/27/2022 CHRIS CHAHBAZ
Miscellaneous Cleared 7/27/2022 CHRIS CHAHBAZ
Sewer availability Cleared 7/27/2022 CHRIS CHAHBAZ
Low Impact Development Cleared 7/28/2022 MARCO SANCHEZ
Grading Pre-Inspection Cleared 8/16/2022 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Pirbadian,, Amir; Lic. No.: C72413 5435 BALBOA BLVD 214      ENCINO, CA 91342

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/17/2022 Approved DAVID SANDOVAL
Footing/Foundation/Slab 12/16/2022 Corrections Issued DAVID SANDOVAL
PLUMBING-Rough 12/16/2022 Partial Approval DAVID SANDOVAL
BUILDING-Rough-Frame 12/20/2022 Corrections Issued VINCENT HANLEY
Footing/Foundation/Slab 12/20/2022 Approved VINCENT HANLEY
Deputy Reinf. Concrete 12/28/2022 Approved VINCENT HANLEY
Deputy Wood Construction 3/22/2023 Approved VINCENT HANLEY
Deputy Wood Construction 3/22/2023 Conditional Approval MORRIS JACKSON
Deputy Wood Construction 4/27/2023 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 4/27/2023 Approved VINCENT HANLEY
Wood Frame 4/27/2023 Partial Approval VINCENT HANLEY
HVAC-Rough 5/5/2023 Corrections Issued VINCENT HANLEY
Wood Frame 6/13/2023 Approved VINCENT HANLEY
ELECTRICAL-Rough 7/12/2023 Approved VINCENT HANLEY
HVAC-Rough 7/12/2023 Approved VINCENT HANLEY
Insulation 7/18/2023 Approved VINCENT HANLEY
Drywall Nailing 7/28/2023 Approved VINCENT HANLEY
ELECTRICAL-Final 8/9/2023 Corrections Issued VINCENT HANLEY
ELECTRICAL-Rough 8/9/2023 Approved VINCENT HANLEY
ELECTRICAL-Rough 8/15/2023 Approved VINCENT HANLEY
Shower Pan 8/23/2023 Approved JOHN KIDWELL
Interior/Exterior Lathing 9/20/2023 Partial Approval VINCENT HANLEY
ELECTRICAL-Final 6/4/2024 Approved THOMAS FINNILA
HVAC-Final 6/4/2024 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Final 6/4/2024 Approved THOMAS FINNILA
HVAC-Final 6/7/2024 Approved THOMAS FINNILA
PLUMBING-Final 6/10/2024 Approved THOMAS FINNILA
BUILDING-Rough-Frame 1/2/2025 Approved JOHN COLEMAN
Final 1/2/2025 Not Ready for Inspection JOHN COLEMAN
Green Building Final 1/2/2025 Not Ready for Inspection JOHN COLEMAN
Green Building Rough 1/2/2025 Approved JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 1/2/2025 SGSOV Approved JOHN COLEMAN
Smoke Detectors 1/2/2025 Partial Inspection JOHN COLEMAN
Final 1/10/2025 OK to Issue CofO JOHN COLEMAN
Green Building Final 1/10/2025 Approved JOHN COLEMAN
Smoke Detectors 1/10/2025 Approved JOHN COLEMAN
Special/Order Compliance 1/22/2025 Partial Inspection JOHN COLEMAN
Special/Order Compliance 1/31/2025 Partial Inspection JOHN COLEMAN
Special/Order Compliance 2/25/2025 Partial Approval JOHN COLEMAN