4130 N STONEYBROOK DR 91403
Certificate Information: 4130 N STONEYBROOK DR 91403
- Application / Permit
- 22014-20000-02036
- Plan Check / Job No.
- B22VN06472
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 16' 9" X 3' 7" LAUNDRY ROOM/WALK IN CLOSET ADDITION, 6' X 9' KITCHEN EXTENSION, CONVERT (E) LAUNDRY TO PANTRY AND RAISE KITCHEN CEILING. ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 12/12/2022
- Issuing Office
- Valley
- Current Status
- CofO Corrected on 8/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2022 | GURUNATH NESARAJAH |
| Corrections Issued | 5/8/2022 | GURUNATH NESARAJAH |
| Plan Check Approved | 7/12/2022 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 7/14/2022 | APPLICANT |
| Issued | 12/12/2022 | APPLICANT |
| CofO in Progress | 5/28/2024 | JACK KARGODORIAN |
| CofO Issued-Status Void | 5/31/2024 | RUBEN SALAS |
| Permit Finaled-Status Void | 5/31/2024 | RUBEN SALAS |
| Re-Activate Permit | 7/30/2025 | RUBEN SALAS |
| Permit Finaled | 8/7/2025 | RUBEN SALAS |
| CofO Corrected | 8/7/2025 | RUBEN SALAS |
| Permit Finaled | 8/7/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/25/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 5/25/2022 | DAGOVERTO GUERRERO |
| Grading Pre-Inspection | Cleared | 7/12/2022 | GURUNATH NESARAJAH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Warling,, Jeffrey Paul; Lic. No.: C43743 | 1792 PEREGRINE CT SIMI VALLEY, CA 93065 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/8/2023 | Partial Approval | JOHN COLEMAN |
| PLUMBING-Rough | 3/8/2023 | Partial Approval | JOHN COLEMAN |
| Footing/Foundation/Slab | 3/13/2023 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 3/20/2023 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Rough | 4/18/2023 | Conditional Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 4/21/2023 | Corrections Issued | THOMAS FINNILA |
| Green Building Rough | 4/21/2023 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 4/21/2023 | Approved | THOMAS FINNILA |
| Deputy Wood Construction | 4/26/2023 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 4/27/2023 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 4/27/2023 | Approved | MATTHEW NELSON |
| Green Building Rough | 4/27/2023 | Approved | MATTHEW NELSON |
| Insulation | 5/3/2023 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 5/3/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Drywall Nailing | 5/5/2023 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 5/5/2023 | Approved | THOMAS FINNILA |
| Final | 4/22/2024 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 4/22/2024 | Approved | THOMAS FINNILA |
| Green Building Final | 4/22/2024 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 4/22/2024 | SGSOV Not Ready | THOMAS FINNILA |
| Smoke Detectors | 4/22/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Final | 5/23/2024 | OK to Issue CofO | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 5/23/2024 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 5/23/2024 | Approved | JACK KARGODORIAN |