8656 N SYLMAR AVE 91402

Certificate Information: 8656 N SYLMAR AVE 91402

Application / Permit
22014-20000-02035
Plan Check / Job No.
B22VN06470
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ECPC: 6'-0" X 8'-2"ADDITION AT REAR, 14'-6" X 23'-5" SF ADDITION AT REAR, AND 5'-0" X 39'-0' ADDIITON AT FRONT, WITH INTERIOR REMODEL TO THE (E) SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 7/14/2022
Issuing Office
Current Status
CofO Issued on 3/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/27/2022 APPLICANT
Assigned to Plan Check Engineer 5/5/2022 LUISANGEL VALENZUELA
Corrections Issued 5/6/2022 LUISANGEL VALENZUELA
Applicant returned to address corrections 7/7/2022 LUISANGEL VALENZUELA
Issued 7/14/2022 APPLICANT
Building Plans Picked Up 7/14/2022 APPLICANT
CofO in Progress 2/17/2023 GREGG CUMMINGS
CofO Issued 3/4/2023 MICHAEL SMITH
Permit Finaled 3/4/2023 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/9/2022 CHRIS CHAHBAZ
Sewer availability Cleared 5/9/2022 CHRIS CHAHBAZ
Low Impact Development Cleared 6/27/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 6/27/2022 CHRIS CHAHBAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/18/2022 Conditional Approval GREGG CUMMINGS
BUILDING-Rough-Frame 7/20/2022 Corrections Issued GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 7/20/2022 Approved GREGG CUMMINGS
Footing/Foundation/Slab 7/20/2022 Approved GREGG CUMMINGS
Special/Order Compliance 7/20/2022 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 7/29/2022 Partial Approval GREGG CUMMINGS
BUILDING-Rough-Frame 8/2/2022 Partial Approval WILLIAM WREN
Insulation 8/2/2022 Partial Approval WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 8/17/2022 Partial Approval GREGG CUMMINGS
ELECTRICAL-Rough 9/1/2022 Corrections Issued WILLIAM WREN
HVAC-Rough 9/1/2022 Approved WILLIAM WREN
PLUMBING-Rough 9/1/2022 Corrections Issued WILLIAM WREN
BUILDING-Rough-Frame 9/7/2022 Corrections Issued CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 9/7/2022 Approved CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 9/7/2022 Approved CHRISTOPHER DELLEFIELD
Green Building Rough 9/7/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
PLUMBING-Rough 9/7/2022 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 9/14/2022 Approved WILLIAM WREN
Green Building Rough 9/14/2022 Approved WILLIAM WREN
Insulation 9/14/2022 Approved WILLIAM WREN
Interior/Exterior Lathing 9/14/2022 Approved WILLIAM WREN
Drywall Nailing 9/27/2022 Approved WILLIAM WREN
Shower Pan 9/27/2022 Approved WILLIAM WREN
Interior/Exterior Lathing 10/6/2022 Approved WILLIAM WREN
Final 1/10/2023 Corrections Issued GREGG CUMMINGS
Green Building Final 1/10/2023 Not Ready for Inspection GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 1/10/2023 SGSOV Not Ready GREGG CUMMINGS
Smoke Detectors 1/10/2023 Not Ready for Inspection GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 2/2/2023 SGSOV Not Ready GREGG CUMMINGS
Final 2/6/2023 Corrections Issued GREGG CUMMINGS
Green Building Final 2/6/2023 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 2/6/2023 SGSOV Not Ready GREGG CUMMINGS
Smoke Detectors 2/6/2023 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Final 2/16/2023 Approved GREGG CUMMINGS
Final 2/16/2023 OK to Issue CofO GREGG CUMMINGS
HVAC-Final 2/16/2023 Approved GREGG CUMMINGS
PLUMBING-Final 2/16/2023 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 2/16/2023 SGSOV Approved GREGG CUMMINGS
Smoke Detectors 2/16/2023 Approved GREGG CUMMINGS