6711 N IRVINE AVE 91606
Certificate Information: 6711 N IRVINE AVE 91606
- Application / Permit
- 22014-20000-02029
- Plan Check / Job No.
- B22VN06454
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 4' X 12' 6" ADDITION OF STORAGE AND LAUNDRY TO THE (E) SFD. ALL WORK PER WFPP.
- Permit Issued
- Issued on 6/30/2022
- Issuing Office
- Current Status
- CofO Issued on 5/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2022 | PINANK PATEL |
| Corrections Issued | 4/28/2022 | PINANK PATEL |
| Applicant returned to address corrections | 6/17/2022 | PINANK PATEL |
| Plan Check Approved | 6/17/2022 | PINANK PATEL |
| No Progress | 6/17/2022 | PINANK PATEL |
| Plan Check Approved | 6/30/2022 | PINANK PATEL |
| Issued | 6/30/2022 | APPLICANT |
| Building Plans Picked Up | 7/1/2022 | APPLICANT |
| CofO in Progress | 5/15/2023 | ROBERT GOLD |
| Permit Finaled | 5/15/2023 | MICHAEL SMITH |
| CofO Issued | 5/15/2023 | MICHAEL SMITH |
| Permit Finaled | 5/15/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/5/2022 | MEGAN GODINEZ |
| ZA Case | Cleared | 5/6/2022 | STEVEN WECHSLER |
| Eng Process Fee Ord 176,300 | Cleared | 5/9/2022 | MEGAN GODINEZ |
Contact Information
| Contractor | Aligned Construction Company Inc; Lic. No.: 894983-B | 8905 GLENOAKS BLVD UNIT L SUN VALLEY, CA 91352 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/20/2022 | Corrections Issued | JOHN HAYES |
| PLUMBING-Rough | 10/27/2022 | Partial Approval | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 11/10/2022 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 1/27/2023 | Not Ready for Inspection | DAVID MATSON |
| ELECTRICAL-Rough | 1/27/2023 | Not Ready for Inspection | DAVID MATSON |
| Green Building Rough | 1/27/2023 | Not Ready for Inspection | DAVID MATSON |
| PLUMBING-Rough | 1/27/2023 | Not Ready for Inspection | DAVID MATSON |
| BUILDING-Rough-Frame | 2/1/2023 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 2/1/2023 | Approved | JOHN HAYES |
| Green Building Rough | 2/1/2023 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 2/1/2023 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 2/16/2023 | Corrections Issued | THOMAS FINNILA |
| BUILDING-Rough-Frame | 2/21/2023 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 2/21/2023 | Partial Approval | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 2/21/2023 | Approved | JOHN HAYES |
| Insulation | 3/14/2023 | Approved | MATTHEW NELSON |
| Drywall Nailing | 3/23/2023 | Approved | JOHN COLEMAN |
| Final | 5/12/2023 | OK to Issue CofO | JOHN HAYES |
| Green Building Final | 5/12/2023 | Approved | JOHN HAYES |
| Smoke Detectors | 5/12/2023 | Approved | JOHN HAYES |