13660 W BRACKEN ST 91331
Certificate Information: 13660 W BRACKEN ST 91331
- Application / Permit
- 22014-20000-02028
- Plan Check / Job No.
- B22VN06452
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: ADDITION AND CONVERT (E) GARAGE TO (N) 1-STORY ACCESSORY DWELLING UNT PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 6/10/2022
- Issuing Office
- Current Status
- CofO Issued on 3/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2022 | DANIEL YIP |
| Corrections Issued | 5/7/2022 | DANIEL YIP |
| Plan Check Approved | 6/1/2022 | DANIEL YIP |
| Issued | 6/10/2022 | APPLICANT |
| CofO in Progress | 1/30/2024 | GREGG CUMMINGS |
| Permit Finaled | 3/2/2024 | RUBEN SALAS |
| CofO Issued | 3/2/2024 | RUBEN SALAS |
| Permit Finaled | 3/2/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/17/2022 | MEGAN GODINEZ |
| Construction near power lines | Cleared | 5/17/2022 | OSCAR CASTRO |
| Roof/Waste drainage to street | Cleared | 5/17/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 5/17/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/19/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 5/19/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 5/19/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 5/19/2022 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/13/2022 | Approved | WILLIAM WREN |
| Footing/Foundation/Slab | 9/13/2022 | Approved | WILLIAM WREN |
| Sewer | 10/14/2022 | Approved | WILLIAM WREN |
| Underground Mechanical | 10/14/2022 | Approved | WILLIAM WREN |
| Pre-Inspection | 1/30/2023 | Approved | GREGG CUMMINGS |
| Deputy Drilled-In Anchors | 5/15/2023 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 9/8/2023 | Corrections Issued | MICHEL ABAJAN |
| ELECTRICAL-Rough | 9/8/2023 | Approved | MICHEL ABAJAN |
| Green Building Rough | 9/8/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 9/8/2023 | Approved | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 11/13/2023 | Approved | CARLOS MATAMOROS |
| Wood Frame | 11/20/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 11/29/2023 | Approved | GREGG CUMMINGS |
| Green Building Rough | 11/29/2023 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 11/29/2023 | Approved | GREGG CUMMINGS |
| Insulation | 12/8/2023 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 12/8/2023 | Approved | GREGG CUMMINGS |
| Shower Pan | 12/8/2023 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 12/12/2023 | Approved | GREGG CUMMINGS |
| Final | 1/24/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 1/24/2024 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 1/24/2024 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 1/24/2024 | Approved | GREGG CUMMINGS |
| Final | 1/29/2024 | OK to Issue CofO | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 1/29/2024 | SGSOV Approved | GREGG CUMMINGS |
| Service/Power Release | 1/29/2024 | Approved | GREGG CUMMINGS |