14723 W LEMAY ST 91405
Certificate Information: 14723 W LEMAY ST 91405
- Application / Permit
- 22014-20000-02026
- Plan Check / Job No.
- B22VN06451
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF 24'-5" X 11'-8" CARPORT TO EXISTING SINGLE FAMILY DWELLING - ALL WORK PER ENGINEER***COMPLY WITH DEPARTMENT ORDER effective date 02/03/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 6/14/2022
- Issuing Office
- Valley
- Current Status
- CofO in Progress on 8/24/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2022 | DANIEL ABRAMYAN |
| Corrections Issued | 4/28/2022 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 5/12/2022 | DANIEL ABRAMYAN |
| Plan Check Approved | 5/26/2022 | DANIEL ABRAMYAN |
| Building Plans Picked Up | 6/6/2022 | APPLICANT |
| Issued | 6/14/2022 | APPLICANT |
| CofO in Progress | 8/24/2022 | MICKEY YAMASHITA |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/2/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/5/2022 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wu,, Harold Ping-Hung; Lic. No.: C35693 | 1168 SAN GABRIEL BLVD NO N ROSEMEAD, CA 91770 |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/5/2022 | Corrections Issued | MICKEY YAMASHITA |
| Footing/Foundation/Slab | 7/12/2022 | Corrections Issued | MICKEY YAMASHITA |
| BUILDING-Rough-Frame | 8/5/2022 | Corrections Issued | MICKEY YAMASHITA |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2022 | Corrections Issued | MICKEY YAMASHITA |
| Footing/Foundation/Slab | 8/5/2022 | Approved | MICKEY YAMASHITA |
| BUILDING-Rough-Frame | 8/9/2022 | Corrections Issued | MICKEY YAMASHITA |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2022 | Approved | MICKEY YAMASHITA |
| Footing/Foundation/Slab | 8/9/2022 | Approved | MICKEY YAMASHITA |
| Green Building Final | 8/9/2022 | Approved | MICKEY YAMASHITA |
| SGSOV-Seismic Gas S/O Valve | 8/9/2022 | SGSOV Not Ready | MICKEY YAMASHITA |
| Smoke Detectors | 8/9/2022 | Approved | MICKEY YAMASHITA |
| BUILDING-Rough-Frame | 8/24/2022 | Approved | MICKEY YAMASHITA |
| ELECTRICAL-Final | 8/24/2022 | Approved | MICKEY YAMASHITA |
| ELECTRICAL-Rough | 8/24/2022 | Approved | MICKEY YAMASHITA |
| Final | 8/24/2022 | OK to Issue CofO | MICKEY YAMASHITA |
| Green Building Rough | 8/24/2022 | Approved | MICKEY YAMASHITA |
| HVAC-Final | 8/24/2022 | Approved | MICKEY YAMASHITA |
| HVAC-Rough | 8/24/2022 | Approved | MICKEY YAMASHITA |
| PLUMBING-Final | 8/24/2022 | Approved | MICKEY YAMASHITA |
| PLUMBING-Rough | 8/24/2022 | Approved | MICKEY YAMASHITA |
| SGSOV-Seismic Gas S/O Valve | 8/24/2022 | SGSOV Approved | MICKEY YAMASHITA |