6858 N BEN AVE 1-16 91605

Certificate Information: 6858 N BEN AVE 1-16 91605

Application / Permit
22014-20000-02020
Plan Check / Job No.
B22VN06443
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
*EPLAN* CONVERT (E) ATTACHED 2-CAR GARAGE TO (1) ADU WITHIN APARTMENT PER CA GC 65852.2(e)(1)(C).
Permit Issued
Issued on 5/18/2022
Issuing Office
Current Status
CofO Issued on 11/2/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/27/2022 APPLICANT
Assigned to Plan Check Engineer 5/3/2022 VIVIAN LAO
Corrections Issued 5/4/2022 VIVIAN LAO
Plan Check Approved 5/18/2022 VIVIAN LAO
Issued 5/18/2022 APPLICANT
CofO in Progress 10/5/2022 ROBERT DAVIS
Permit Finaled 11/2/2022 JEFFREY DURAN
CofO Issued 11/2/2022 JEFFREY DURAN
Permit Finaled 11/2/2022 JEFFREY DURAN

Permit Application Clearance Information

Address approval Cleared 5/10/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 5/10/2022 ROMAN GUTIERREZ
Sewer availability Cleared 5/10/2022 ROMAN GUTIERREZ
Tenant Habitability Plan Cleared 5/12/2022 MICHAEL SOTO

Contact Information

Contractor Sauer Paul Construction; Lic. No.: 1079869-B       ,
Engineer Zohrevand,, Pedram; Lic. No.: C82328 19562 VENTURA BLVD UNIT 238      TARZANA, CA 91356

Inspector Information

JEFFREY FULTON, (818) 374-1132 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/23/2022 Conditional Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 6/24/2022 Approved ROBERT DAVIS
Footing/Foundation/Slab 6/24/2022 Approved ROBERT DAVIS
Green Building Rough 6/28/2022 Not Ready for Inspection ROBERT DAVIS
Wood Frame 6/28/2022 Not Ready for Inspection ROBERT DAVIS
Green Building Rough 6/30/2022 Approved ROBERT DAVIS
Wood Frame 6/30/2022 Partial Approval ROBERT DAVIS
Insulation 7/8/2022 Approved ROBERT DAVIS
Interior/Exterior Lathing 7/8/2022 Partial Approval ROBERT DAVIS
Wood Frame 7/8/2022 Approved ROBERT DAVIS
Drywall Nailing 7/13/2022 Approved ROBERT DAVIS
Final 7/27/2022 OK to Issue CofO ROBERT DAVIS
Green Building Final 7/27/2022 Approved ROBERT DAVIS
SGSOV-Seismic Gas S/O Valve 7/27/2022 SGSOV Approved ROBERT DAVIS
Smoke Detectors 7/27/2022 Approved ROBERT DAVIS