13155 W CARL ST 91331
Certificate Information: 13155 W CARL ST 91331
- Application / Permit
- 22014-20000-02017
- Plan Check / Job No.
- B22VN06436
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 15'-6" x 22'-3" (319 SQ. FT.) TO THE (E) SFD FOR STORAGE, 3/4 BATHROOM, AND JOIN THE SFD TO THE DETACHED CARPORT
- Permit Issued
- Issued on 8/4/2022
- Issuing Office
- Valley
- Current Status
- Issued on 8/4/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/4/2022 | OMAR GARNICA |
| Corrections Issued | 5/7/2022 | OMAR GARNICA |
| Building Plans Picked Up | 5/23/2022 | APPLICANT |
| Applicant returned to address corrections | 7/28/2022 | ANGELICA DAVE |
| Plan Check Approved | 8/1/2022 | ALEC MOUSAKHANIAN |
| Issued | 8/4/2022 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/12/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/24/2022 | ROMAN GUTIERREZ |
| Public Works-Highway Ded. | Cleared | 5/24/2022 | ROMAN GUTIERREZ |
| Public Works-Open Permits | Cleared | 5/24/2022 | ROMAN GUTIERREZ |
| Public Works-Sewers | Cleared | 5/24/2022 | ROMAN GUTIERREZ |
| ZI | Cleared | 6/21/2022 | DANG NGUYEN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/26/2023 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 1/26/2023 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 1/26/2023 | Approved | JENNIFER RABUCHIN |
| METHANE-Barrier | 1/26/2023 | Approved | JENNIFER RABUCHIN |
| METHANE-Subgrade | 1/26/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 1/26/2023 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2023 | Corrections Issued | MICHEL ABAJAN |
| Green Building Rough | 2/15/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| METHANE-Rough | 2/15/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 4/18/2023 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 4/18/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 4/18/2023 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 6/3/2025 | Corrections Issued | MATTHEW NELSON |
| Green Building Rough | 6/3/2025 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 8/13/2025 | Approved | MICHEL ABAJAN |
| Green Building Rough | 8/13/2025 | Approved | MICHEL ABAJAN |
| Insulation | 9/25/2025 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 9/25/2025 | Partial Approval | JENNIFER RABUCHIN |
| Drywall Nailing | 12/11/2025 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 12/11/2025 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 3/6/2026 | Approved | MICHEL ABAJAN |