24668 W OVERLAND DR 91304

Certificate Information: 24668 W OVERLAND DR 91304

Application / Permit
22014-20000-02010
Plan Check / Job No.
B22VN06422
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
50'0"X67'0" IRREGULAR SHAPED 1-STORY ADDITION AND MAJOR REMODEL TO (E) 2-STORY SINGLE FAMILY DWELLING WITH EXISTING ATTACHED 3-CAR GARAGE. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 10/24/2022
Issuing Office
Valley
Current Status
CofO Issued on 11/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/26/2022 APPLICANT
Assigned to Plan Check Engineer 5/19/2022 COLIN LOREDO
Corrections Issued 5/26/2022 COLIN LOREDO
Quality Review Completed 6/1/2022 OMID HEDAYAT
Building Plans Picked Up 6/2/2022 APPLICANT
Applicant returned to address corrections 9/20/2022 MARVEL DELACRUZ
Plan Check Approved 10/12/2022 MARVEL DELACRUZ
Issued 10/24/2022 APPLICANT
CofO in Progress 10/31/2024 JEFFREY HARTLINE
CofO Issued 11/7/2024 JOHN JANSON
Permit Finaled 11/7/2024 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/10/2022 MEGAN GODINEZ
Miscellaneous Cleared 6/10/2022 DANIEL CORONADO
Sewer availability Cleared 6/10/2022 MEGAN GODINEZ
Hydrant and Access approval Cleared 7/22/2022 KURT CORRAL
Low Impact Development Cleared 9/6/2022 MITESH PATEL
Roof/Waste drainage to street Cleared 9/8/2022 COLIN LOREDO
Grading Pre-Inspection Cleared 9/20/2022 BRIAN MILLER
GPI Written Notices Cleared 10/12/2022 COLIN LOREDO

Contact Information

Contractor Jerseyboy Construction; Lic. No.: 1010576-B 1639 S CARMELINA AVE      LOS ANGELES, CA 90025
Engineer Niver,, Kenneth Earl; Lic. No.: S2554 10845 LINDBROOK DR STE 203      W LOS ANGELES, CA 90024

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/17/2022 Conditional Approval CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 11/30/2022 Partial Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 11/30/2022 Partial Approval CHRIS CHRISTENSEN
Underground Mechanical 11/30/2022 Partial Approval CHRIS CHRISTENSEN
Deputy Drilled-In Anchors 12/8/2022 Conditional Approval CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 1/18/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Underground Mechanical 1/18/2023 Partial Approval CHRIS CHRISTENSEN
Deputy Steel/Welding 1/23/2023 Conditional Approval CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 2/14/2023 Partial Approval CHRIS CHRISTENSEN
Deputy Reinf. Concrete 2/17/2023 Conditional Approval CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 6/7/2023 Approved CHRIS CHRISTENSEN
Footing/Foundation/Slab 6/7/2023 Approved CHRIS CHRISTENSEN
Wood Frame 6/7/2023 Partial Approval CHRIS CHRISTENSEN
Deputy Reinf. Concrete 6/9/2023 Conditional Approval HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 9/11/2023 Partial Approval CHRIS CHRISTENSEN
Gas Test 10/2/2023 Approved JEFFREY HARTLINE
PLUMBING-Rough 10/2/2023 Partial Approval JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 10/2/2023 SGSOV Approved JEFFREY HARTLINE
Underground Mechanical 10/2/2023 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 1/3/2024 Not Ready for Inspection JEFFREY HARTLINE
ELECTRICAL-Rough 1/3/2024 Approved JEFFREY HARTLINE
Green Building Rough 1/3/2024 Not Ready for Inspection JEFFREY HARTLINE
HVAC-Rough 1/3/2024 Approved JEFFREY HARTLINE
PLUMBING-Rough 1/3/2024 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 1/12/2024 Approved JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 1/12/2024 Approved JEFFREY HARTLINE
Green Building Rough 1/12/2024 Approved JEFFREY HARTLINE
HVAC-Rough 1/12/2024 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 1/12/2024 Partial Approval JEFFREY HARTLINE
Insulation 1/24/2024 Approved JEFFREY HARTLINE
Drywall Nailing 2/6/2024 Approved JEFFREY HARTLINE
Shower Pan 2/13/2024 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 2/16/2024 Partial Approval JEFFREY HARTLINE
Interior/Exterior Lathing 3/21/2024 Partial Approval HENRY KIM
Gas Test 5/31/2024 Approved JEFFREY HARTLINE
Underground Mechanical 5/31/2024 Partial Approval JEFFREY HARTLINE
Interior/Exterior Lathing 8/7/2024 Partial Approval JEFFREY HARTLINE
ELECTRICAL-Final 9/9/2024 Not Ready for Inspection JEFFREY HARTLINE
HVAC-Final 9/9/2024 Approved JEFFREY HARTLINE
PLUMBING-Final 9/9/2024 Approved JEFFREY HARTLINE
ELECTRICAL-Final 10/7/2024 Approved CHRIS CHRISTENSEN
Final 10/25/2024 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 10/25/2024 Approved CHRIS CHRISTENSEN
Smoke Detectors 10/25/2024 Approved CHRIS CHRISTENSEN
Structural Steel Frame 10/25/2024 Approved CHRIS CHRISTENSEN
Final 10/30/2024 OK to Issue CofO JEFFREY HARTLINE