6150 N PETERSON AVE 91367
Certificate Information: 6150 N PETERSON AVE 91367
- Application / Permit
- 22014-20000-01996
- Plan Check / Job No.
- B22VN06350
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 15' 4" X 43' 8" REAR ADDITION TO (E) SFD AND REMOVE KITCHEN WALLS. ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 12/22/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2022 | GURUNATH NESARAJAH |
| Corrections Issued | 5/1/2022 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 5/3/2022 | APPLICANT |
| Plan Check Approved | 10/26/2022 | ALEC MOUSAKHANIAN |
| Issued | 12/22/2022 | APPLICANT |
| CofO in Progress | 8/18/2023 | TROY SANDERS |
| Permit Finaled | 9/14/2023 | JOHN JANSON |
| CofO Issued | 9/14/2023 | JOHN JANSON |
| Permit Finaled | 9/14/2023 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/17/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 5/17/2022 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 10/7/2022 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 10/12/2022 | DAGOVERTO GUERRERO |
Contact Information
| Architect | Miller,, Michael; Lic. No.: C26956 | 12756 MITCHELL AVE LOS ANGELES, CA 90066 |
| Contractor | Owner-Builder | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 1/6/2023 | Corrections Issued | SEAN WIRCH |
| Final | 1/6/2023 | Corrections Issued | SEAN WIRCH |
| Footing/Foundation/Slab | 1/6/2023 | Corrections Issued | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 1/6/2023 | SGSOV Not Ready | SEAN WIRCH |
| Footing/Foundation/Slab | 4/20/2023 | Approved | TROY SANDERS |
| Pre-Inspection | 4/20/2023 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 6/9/2023 | Partial Approval | HORACE FULTZ |
| Green Building Rough | 6/9/2023 | Approved | HORACE FULTZ |
| Wood Frame | 6/9/2023 | Partial Approval | HORACE FULTZ |
| Insulation | 6/21/2023 | Approved | TROY SANDERS |
| Smoke Detectors | 6/21/2023 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 8/17/2023 | Approved | TROY SANDERS |
| ELECTRICAL-Final | 8/17/2023 | Approved | TROY SANDERS |
| Final | 8/17/2023 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 8/17/2023 | Approved | TROY SANDERS |
| HVAC-Final | 8/17/2023 | Approved | TROY SANDERS |
| PLUMBING-Final | 8/17/2023 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 8/17/2023 | SGSOV Approved | TROY SANDERS |