5644 N PONCE AVE 91367

Certificate Information: 5644 N PONCE AVE 91367

Application / Permit
22014-20000-01988
Plan Check / Job No.
B22VN06347
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: CONVERT (E) GARAGE TO (N) 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 7/11/2022
Issuing Office
Current Status
CofO Issued on 3/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/28/2022 APPLICANT
Assigned to Plan Check Engineer 5/6/2022 DANIEL YIP
Corrections Issued 5/7/2022 DANIEL YIP
Plan Check Approved 5/17/2022 DANIEL YIP
Issued 7/11/2022 APPLICANT
CofO in Progress 2/6/2023 TROY SANDERS
Permit Finaled 3/9/2023 DANIEL ORRANTE
CofO Issued 3/9/2023 DANIEL ORRANTE
Permit Finaled 3/9/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 5/13/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 5/13/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 5/16/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/21/2022 Partial Approval JESUS PINEDA
Footing/Foundation/Slab 7/27/2022 Corrections Issued DAVID SANDOVAL
Footing/Foundation/Slab 8/2/2022 Approved PETER FOLLING
ELECTRICAL-Rough 8/24/2022 Approved TROY SANDERS
Insulation 8/24/2022 Partial Approval TROY SANDERS
PLUMBING-Rough 8/24/2022 Approved TROY SANDERS
BUILDING-Rough-Frame 9/21/2022 Partial Approval TROY SANDERS
HVAC-Rough 9/21/2022 Approved TROY SANDERS
Green Building Rough 9/29/2022 Approved JESUS PINEDA
Insulation 9/29/2022 Approved JESUS PINEDA
Interior/Exterior Lathing 9/29/2022 Partial Approval JESUS PINEDA
Drywall Nailing 10/18/2022 Approved JUSTIN HAWLEY
Shower Pan 10/18/2022 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 10/25/2022 Approved JUSTIN HAWLEY
ELECTRICAL-Final 11/15/2022 Approved TROY SANDERS
HVAC-Final 11/15/2022 Not Ready for Inspection TROY SANDERS
Service/Power Release 11/15/2022 Approved TROY SANDERS
BUILDING-Rough-Frame 11/23/2022 No Access for Inspection TROY SANDERS
Final 11/23/2022 No Access for Inspection TROY SANDERS
Gas Test 11/23/2022 Not Ready for Inspection TROY SANDERS
HVAC-Final 11/23/2022 No Access for Inspection TROY SANDERS
SGSOV-Seismic Gas S/O Valve 11/23/2022 SGSOV Not Ready TROY SANDERS
Smoke Detectors 11/23/2022 No Access for Inspection TROY SANDERS
Gas Test 12/1/2022 Approved ALEXANDER HANDY
HVAC-Final 12/1/2022 Corrections Issued ALEXANDER HANDY
Service/Power Release 12/1/2022 Not Ready for Inspection ALEXANDER HANDY
BUILDING-Rough-Frame 1/4/2023 Approved TROY SANDERS
Final 1/4/2023 Corrections Issued TROY SANDERS
SGSOV-Seismic Gas S/O Valve 1/4/2023 SGSOV Not Ready TROY SANDERS
Smoke Detectors 1/4/2023 Approved TROY SANDERS
Final 2/6/2023 OK to Issue CofO TROY SANDERS
SGSOV-Seismic Gas S/O Valve 2/6/2023 SGSOV Approved TROY SANDERS