18946-18948 W CALVERT ST 91335

Certificate Information: 18946-18948 W CALVERT ST 91335

Application / Permit
22014-20000-01987
Plan Check / Job No.
B22VN06346
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan (E) 2-CAR ATTACHED GARAGE CONVERT TO ADU WITH ADDITION plancheck per LAMC 12.22 A.33(C) AND (E)
Permit Issued
Issued on 5/18/2022
Issuing Office
Current Status
CofO Issued on 10/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/1/2022 APPLICANT
Assigned to Plan Check Engineer 5/6/2022 SUNMIN LEE
Corrections Issued 5/9/2022 SUNMIN LEE
Applicant returned to address corrections 5/16/2022 SUNMIN LEE
Plan Check Approved 5/17/2022 SUNMIN LEE
Issued 5/18/2022 APPLICANT
CofO in Progress 9/8/2022 SEAN HAUPT
CofO in Progress 9/16/2022 SEAN HAUPT
Permit Finaled 10/4/2022 JOHN JANSON
CofO Issued 10/4/2022 JOHN JANSON

Permit Application Clearance Information

ZI Cleared 5/9/2022 DANG NGUYEN
Address approval Cleared 5/10/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 5/10/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 5/11/2022 CARLOS AGUILERA
Sewer availability Cleared 5/11/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Levin,, Vladimir; Lic. No.: C35001 11606 CHENAULT STR, UNIT 301      LOS ANGELES, CA 90049

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/27/2022 Approved SEAN HAUPT
Footing/Foundation/Slab 6/9/2022 Approved SEAN HAUPT
ELECTRICAL-Rough 6/28/2022 Approved SEAN HAUPT
PLUMBING-Rough 6/28/2022 Not Ready for Inspection SEAN HAUPT
HVAC-Rough 7/5/2022 Not Ready for Inspection SEAN HAUPT
PLUMBING-Rough 7/5/2022 Approved SEAN HAUPT
HVAC-Rough 7/8/2022 Approved SEAN HAUPT
Interior/Exterior Lathing 7/12/2022 Approved MORRIS JACKSON
Drywall Nailing 7/20/2022 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 7/26/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 8/25/2022 Approved SEAN HAUPT
Final 8/25/2022 Not Ready for Inspection SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 8/25/2022 SGSOV Not Ready SEAN HAUPT
Smoke Detectors 8/25/2022 Not Ready for Inspection SEAN HAUPT
Underground Mechanical 8/25/2022 Approved SEAN HAUPT
Final 8/30/2022 Corrections Issued SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 8/30/2022 SGSOV Approved SEAN HAUPT
Smoke Detectors 8/30/2022 Approved SEAN HAUPT
Final 9/7/2022 OK to Issue CofO SEAN HAUPT
Green Building Final 9/7/2022 Approved SEAN HAUPT