11032 N DEMPSEY AVE 91344

Certificate Information: 11032 N DEMPSEY AVE 91344

Application / Permit
22014-20000-01984
Plan Check / Job No.
B22VN06342
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING
Permit Issued
Issued on 6/10/2022
Issuing Office
Current Status
CofO Issued on 4/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/26/2022 APPLICANT
Assigned to Plan Check Engineer 4/27/2022 DANIEL YIP
Corrections Issued 4/28/2022 DANIEL YIP
Applicant returned to address corrections 5/3/2022 DANIEL YIP
Applicant returned to address corrections 5/24/2022 DANIEL YIP
Plan Check Approved 6/4/2022 DANIEL YIP
Issued 6/10/2022 APPLICANT
CofO in Progress 4/26/2023 JAVIER RAMOS JR
Permit Finaled 4/26/2023 MICHAEL SMITH
CofO Issued 4/26/2023 MICHAEL SMITH
Permit Finaled 4/26/2023 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/25/2022 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 5/25/2022 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 5/25/2022 MEGAN GODINEZ
Public Works-Open Permits Cleared 5/25/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 5/25/2022 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Itani,, Riad Hassan; Lic. No.: C55688 2459 W 228TH ST      TORRANCE, CA 90501

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/2/2022 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 8/10/2022 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 8/10/2022 Approved JAVIER RAMOS JR
Deputy Wood Construction 8/29/2022 Conditional Approval JAVIER RAMOS JR
Insulation 8/31/2022 Partial Approval JAVIER RAMOS JR
Pre-Inspection 8/31/2022 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 9/20/2022 Partial Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 9/20/2022 Approved JAVIER RAMOS JR
Green Building Rough 9/20/2022 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Rough 9/20/2022 Approved JAVIER RAMOS JR
PLUMBING-Rough 9/20/2022 Approved JAVIER RAMOS JR
Deputy Wood Construction 9/23/2022 Conditional Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 9/28/2022 Partial Approval DEANDRE HOFFMAN
Green Building Rough 9/28/2022 Approved DEANDRE HOFFMAN
Insulation 9/28/2022 Corrections Issued DEANDRE HOFFMAN
Interior/Exterior Lathing 10/20/2022 Approved JAVIER RAMOS JR
Drywall Nailing 10/25/2022 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 4/5/2023 Approved JAVIER RAMOS JR
Final 4/5/2023 Corrections Issued JAVIER RAMOS JR
Green Building Final 4/5/2023 Not Ready for Inspection JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 4/5/2023 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 4/5/2023 Approved JAVIER RAMOS JR
Final 4/26/2023 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 4/26/2023 Approved JAVIER RAMOS JR