15239 W OTSEGO ST 91403

Certificate Information: 15239 W OTSEGO ST 91403

Application / Permit
22014-20000-01976
Plan Check / Job No.
B22VN06321
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED 20' 3" X 12' HOBBY ROOM AND 20' 3" X 20' 2-CAR GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK DONE PER WFPP.
Permit Issued
Issued on 8/26/2022
Issuing Office
Valley
Current Status
CofO Issued on 7/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/27/2022 APPLICANT
Assigned to Plan Check Engineer 5/5/2022 LUISANGEL VALENZUELA
Corrections Issued 5/6/2022 LUISANGEL VALENZUELA
Plan Check Approved 7/29/2022 GURUNATH NESARAJAH
Issued 8/26/2022 APPLICANT
CofO in Progress 4/16/2024 THOMAS FINNILA
Permit Finaled 7/17/2024 RUBEN SALAS
CofO Issued 7/17/2024 RUBEN SALAS
Permit Finaled 7/17/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/23/2022 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 5/23/2022 MEGAN GODINEZ
Sewer availability Cleared 5/24/2022 MEGAN GODINEZ
Construction near power lines Cleared 7/23/2022 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 7/27/2022 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 7/27/2022 MEGAN GODINEZ
Public Works-Open Permits Cleared 7/27/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 7/27/2022 MEGAN GODINEZ

Contact Information

Contractor R M Home Renovation And Design Inc; Lic. No.: 1059814-B 5301 BALBOA BLVD UNIT E1      ENCINO, CA 91316

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/13/2022 Not Ready for Inspection JACK KARGODORIAN
Sewer 9/13/2022 Not Ready for Inspection JACK KARGODORIAN
Deputy Drilled-In Anchors 9/23/2022 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 9/23/2022 Approved JACK KARGODORIAN
PLUMBING-Rough 9/23/2022 Partial Approval JACK KARGODORIAN
Sewer 9/23/2022 Approved JACK KARGODORIAN
Rough-Elec/Plmb/HVAC 8/21/2023 Corrections Issued THOMAS FINNILA
BUILDING-Rough-Frame 11/8/2023 Partial Approval RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 11/8/2023 Partial Approval RUBEN SALAS
Green Building Rough 11/8/2023 Not Ready for Inspection RUBEN SALAS
Pre-Inspection 11/8/2023 Partial Inspection RUBEN SALAS
Rough-Elec/Plmb/HVAC 11/8/2023 Partial Inspection RUBEN SALAS
Insulation 12/5/2023 Not Ready for Inspection THOMAS FINNILA
Interior/Exterior Lathing 12/5/2023 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 12/5/2023 Corrections Issued THOMAS FINNILA
Deputy Drilled-In Anchors 12/6/2023 Conditional Approval DAVID MATSON
ELECTRICAL-Rough 12/11/2023 Approved THOMAS FINNILA
HVAC-Rough 12/11/2023 Approved THOMAS FINNILA
PLUMBING-Rough 12/11/2023 Approved THOMAS FINNILA
Wood Frame 12/11/2023 Approved THOMAS FINNILA
Drywall Nailing 12/18/2023 Approved THOMAS FINNILA
Interior/Exterior Lathing 12/21/2023 Not Ready for Inspection THOMAS FINNILA
Shower Pan 12/21/2023 Corrections Issued THOMAS FINNILA
Interior/Exterior Lathing 12/22/2023 Approved THOMAS FINNILA
Shower Pan 12/22/2023 Approved THOMAS FINNILA
ELECTRICAL-Rough 2/15/2024 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 3/15/2024 Not Ready for Inspection THOMAS FINNILA
Final 3/15/2024 Not Ready for Inspection THOMAS FINNILA
HVAC-Final 3/15/2024 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Final 3/15/2024 Not Ready for Inspection THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 3/15/2024 SGSOV Not Ready THOMAS FINNILA
BUILDING-Rough-Frame 4/1/2024 Approved THOMAS FINNILA
ELECTRICAL-Final 4/1/2024 Not Ready for Inspection THOMAS FINNILA
Final 4/1/2024 Corrections Issued THOMAS FINNILA
Green Building Final 4/1/2024 Approved THOMAS FINNILA
Green Building Rough 4/1/2024 Approved THOMAS FINNILA
HVAC-Final 4/1/2024 Corrections Issued THOMAS FINNILA
PLUMBING-Final 4/1/2024 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 4/1/2024 SGSOV Not Ready THOMAS FINNILA
Smoke Detectors 4/1/2024 Approved THOMAS FINNILA
ELECTRICAL-Final 4/8/2024 Approved THOMAS FINNILA
Final 4/8/2024 Corrections Issued THOMAS FINNILA
HVAC-Final 4/8/2024 Approved THOMAS FINNILA
PLUMBING-Final 4/8/2024 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 4/8/2024 SGSOV Approved THOMAS FINNILA
Enclosure/Fence 4/10/2024 Approved THOMAS FINNILA
Final 4/12/2024 OK to Issue CofO THOMAS FINNILA
Service/Power Release 4/12/2024 Approved THOMAS FINNILA