7804 N KENTLAND AVE 91304

Certificate Information: 7804 N KENTLAND AVE 91304

Application / Permit
22014-20000-01972
Plan Check / Job No.
B22VN06310
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
16'6" X 18' ADDITION TO AND CONVERT (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 5/19/2022
Issuing Office
Current Status
CofO Issued on 11/9/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/25/2022 APPLICANT
Assigned to Plan Check Engineer 4/29/2022 PINANK PATEL
Corrections Issued 4/30/2022 PINANK PATEL
Building Plans Picked Up 5/2/2022 APPLICANT
Plan Check Approved 5/18/2022 PINANK PATEL
Issued 5/19/2022 APPLICANT
CofO in Progress 11/2/2022 CHRIS CHRISTENSEN
Permit Finaled 11/9/2022 JOHN JANSON
CofO Issued 11/9/2022 JOHN JANSON
Permit Finaled 11/9/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/2/2022 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 5/2/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 5/3/2022 MEGAN GODINEZ
Sewer availability Cleared 5/3/2022 MEGAN GODINEZ

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/3/2022 Partial Approval CHRIS CHRISTENSEN
Underground Mechanical 6/3/2022 Partial Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 6/9/2022 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 6/28/2022 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 6/28/2022 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Rough 6/28/2022 Not Ready for Inspection CHRIS CHRISTENSEN
BUILDING-Rough-Frame 7/21/2022 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 7/21/2022 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Rough 7/21/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 7/21/2022 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 7/27/2022 Approved CHRIS CHRISTENSEN
Green Building Rough 7/27/2022 Approved CHRIS CHRISTENSEN
Insulation 7/27/2022 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 7/27/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Shower Pan 7/27/2022 Approved CHRIS CHRISTENSEN
Drywall Nailing 8/1/2022 Approved JESUS PINEDA
Interior/Exterior Lathing 8/1/2022 Approved JESUS PINEDA
ELECTRICAL-Final 10/17/2022 Approved CHRIS CHRISTENSEN
Final 10/17/2022 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 10/17/2022 Corrections Issued CHRIS CHRISTENSEN
HVAC-Final 10/17/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Final 10/17/2022 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 10/17/2022 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 10/17/2022 Approved CHRIS CHRISTENSEN
Final 10/25/2022 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 10/25/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Final 11/1/2022 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 11/1/2022 Approved CHRIS CHRISTENSEN