1727 S SPAULDING AVE 90019
Certificate Information: 1727 S SPAULDING AVE 90019
- Application / Permit
- 22014-20000-01970
- Plan Check / Job No.
- B22VN06305
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18' X 18' DETACHED GARAGE AND ADD 6' X 18' TO CREATE (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 1/3/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2022 | RAPHAEL ROSAS |
| Corrections Issued | 5/9/2022 | RAPHAEL ROSAS |
| Quality Review Completed | 5/12/2022 | STEVEN KIM |
| Building Plans Picked Up | 5/16/2022 | APPLICANT |
| Applicant returned to address corrections | 12/20/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 12/27/2022 | RAPHAEL ROSAS |
| Issued | 1/3/2023 | APPLICANT |
| CofO in Progress | 2/1/2024 | BRENDAN MORELLI |
| Permit Finaled | 2/5/2024 | DEROLD HAUFF |
| CofO Issued | 2/5/2024 | DEROLD HAUFF |
| Permit Finaled | 2/5/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/18/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 10/21/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 10/21/2022 | AMAAN MALIK |
| Construction near power lines | Cleared | 11/16/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 12/21/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 12/30/2022 | TREVOR QUAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/4/2023 | Off-Hour Fees Due | |
| Deputy Drilled-In Anchors | 4/5/2023 | Conditional Approval | JOSE AVILA |
| Footing/Foundation/Slab | 4/6/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| METHANE-Barrier | 4/6/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| METHANE-Subgrade | 4/6/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Pre-Inspection | 4/6/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 4/11/2023 | Approved | JOSE AVILA |
| METHANE-Subgrade | 4/28/2023 | No Access for Inspection | JOSE AVILA |
| Deputy Reinf. Concrete | 5/8/2023 | Conditional Approval | JOSE AVILA |
| Pre-Inspection | 5/25/2023 | Corrections Issued | JOSE AVILA |
| Pre-Inspection | 5/25/2023 | Off-Hour Fees Due | |
| Deputy Drilled-In Anchors | 5/26/2023 | Conditional Approval | JOSE AVILA |
| Footing/Foundation/Slab | 6/1/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| METHANE-Barrier | 6/1/2023 | Conditional Approval | ALIZAH MAYAGOITIA |
| METHANE-Subgrade | 6/1/2023 | Conditional Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 6/6/2023 | Approved | JOSE AVILA |
| METHANE-Barrier | 6/6/2023 | Approved | JOSE AVILA |
| METHANE-Subgrade | 6/6/2023 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 7/3/2023 | Corrections Issued | JOSE AVILA |
| METHANE-Rough | 7/3/2023 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2023 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 7/20/2023 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 7/20/2023 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 8/1/2023 | Not Ready for Inspection | JOSE AVILA |
| ELECTRICAL-Rough | 8/11/2023 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 8/11/2023 | Not Ready for Inspection | JOSE AVILA |
| PLUMBING-Rough | 8/11/2023 | Corrections Issued | JOSE AVILA |
| Underground Mechanical | 8/11/2023 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 8/17/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 8/24/2023 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 8/24/2023 | Approved | JOSE AVILA |
| Drywall Nailing | 9/21/2023 | Approved | JOSE AVILA |
| Green Building Rough | 9/21/2023 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 9/25/2023 | Approved | RONNIE MINDANAO |
| Gas Test | 10/2/2023 | Not Ready for Inspection | JOSE AVILA |
| Final | 12/13/2023 | Corrections Issued | SCOTT FINNILA |
| Green Building Final | 12/13/2023 | Approved | SCOTT FINNILA |
| HVAC-Final | 12/13/2023 | Approved | SCOTT FINNILA |
| PLUMBING-Final | 12/13/2023 | Approved | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 12/13/2023 | SGSOV Approved | SCOTT FINNILA |
| Smoke Detectors | 12/13/2023 | Approved | SCOTT FINNILA |
| Final | 12/19/2023 | Corrections Issued | RONNIE MINDANAO |
| Final | 1/30/2024 | Conditional Approval | BRENDAN MORELLI |
| Final | 2/1/2024 | OK to Issue CofO | BRENDAN MORELLI |