8611 N TELFAIR AVE 91352

Certificate Information: 8611 N TELFAIR AVE 91352

Application / Permit
22014-20000-01966
Plan Check / Job No.
B22VN06296
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan ADDITION TO (E) SFD
Permit Issued
Issued on 6/21/2022
Issuing Office
Current Status
CofO Issued on 12/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/1/2022 APPLICANT
Assigned to Plan Check Engineer 5/6/2022 FERNANDO FLORES
Corrections Issued 5/7/2022 FERNANDO FLORES
Plan Check Approved 6/8/2022 FERNANDO FLORES
Issued 6/21/2022 APPLICANT
CofO in Progress 12/9/2022 MATTHEW NELSON
CofO Issued 12/24/2022 MICHAEL SMITH
Permit Finaled 12/24/2022 MICHAEL SMITH

Permit Application Clearance Information

"Q" conditions Cleared 5/12/2022 STEVEN WECHSLER
"T" removal Cleared 5/12/2022 STEVEN WECHSLER
Roof/Waste drainage to street Cleared 5/12/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 5/16/2022 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 5/16/2022 MEGAN GODINEZ
Public Works-Open Permits Cleared 5/16/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 5/16/2022 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Hajdari,, Genti; Lic. No.: C88031 140 S MENTOR AVE APT #207      PASADENA, CA 91106

Inspector Information

WILLIAM WREN, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/24/2022 Conditional Approval MICHAEL SMITH
Footing/Foundation/Slab 6/29/2022 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Rough 6/29/2022 Partial Approval CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 7/13/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 7/13/2022 Corrections Issued CHRISTOPHER DELLEFIELD
MERV13>=Rough 7/13/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 8/9/2022 Corrections Issued CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 8/9/2022 Approved CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 8/9/2022 Approved CHRISTOPHER DELLEFIELD
HVAC-Rough 8/9/2022 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Rough 8/9/2022 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 8/15/2022 Approved CHRISTOPHER DELLEFIELD
Green Building Rough 8/15/2022 Approved CHRISTOPHER DELLEFIELD
MERV13>=Rough 8/15/2022 Approved CHRISTOPHER DELLEFIELD
Wood Frame 8/15/2022 Approved CHRISTOPHER DELLEFIELD
Insulation 8/17/2022 Partial Approval CHRISTOPHER DELLEFIELD
Drywall Nailing 8/19/2022 Conditional Approval CHRISTOPHER DELLEFIELD
Drywall Nailing 8/22/2022 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 8/22/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Shower Pan 8/22/2022 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 8/24/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 8/29/2022 Approved WILLIAM WREN
Final 11/1/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 11/1/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
MERV13>=Final 11/1/2022 Corrections Issued CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 11/1/2022 SGSOV Not Ready CHRISTOPHER DELLEFIELD
Smoke Detectors 11/1/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 11/16/2022 Approved CHRISTOPHER DELLEFIELD
Final 11/16/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 11/16/2022 Approved CHRISTOPHER DELLEFIELD
HVAC-Final 11/16/2022 Approved CHRISTOPHER DELLEFIELD
MERV13>=Final 11/16/2022 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Final 11/16/2022 Approved CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 11/16/2022 SGSOV Approved CHRISTOPHER DELLEFIELD
HVAC-Final 12/6/2022 Approved MATTHEW NELSON
Final 12/8/2022 OK to Issue CofO MATTHEW NELSON