1601 N LINDAMERE PL 90077
Certificate Information: 1601 N LINDAMERE PL 90077
- Application / Permit
- 22014-20000-01965
- Plan Check / Job No.
- B22VN06295
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL WITH 1ST AND 2ND STORY ADDITION TO THE EXISTING 2-STORY SINGLE FAMILY DWELLING. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 6/24/2022
- Issuing Office
- Current Status
- CofO Issued on 6/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2022 | COLIN LOREDO |
| Corrections Issued | 5/9/2022 | COLIN LOREDO |
| Quality Review Completed | 5/13/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 5/13/2022 | APPLICANT |
| Plan Check Approved | 6/16/2022 | COLIN LOREDO |
| Issued | 6/24/2022 | APPLICANT |
| CofO in Progress | 6/14/2023 | CHRISTOPHER WILSON |
| Permit Finaled | 6/26/2023 | DANIEL ORRANTE |
| CofO Issued | 6/26/2023 | DANIEL ORRANTE |
| Permit Finaled | 6/26/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 5/25/2022 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 5/25/2022 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 5/25/2022 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 5/25/2022 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 5/25/2022 | DINAH GARIN |
| Sewer availability | Cleared | 5/25/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 5/27/2022 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 6/14/2022 | GILBERT URREA |
| GPI Written Notices | Cleared | 6/16/2022 | COLIN LOREDO |
| Grading Pre-Inspection | Cleared | 6/16/2022 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 6/18/2022 | SAUL GARCIA |
Contact Information
| Architect | Heeb,, Derek M; Lic. No.: C32338 | 406 BROADWAY 222C SANTA MONICA, CA 90401 |
| Contractor | Corr Contemporary Homes Llc; Lic. No.: 913500-B | 13428 MAXELLA AVENUE #816 MARINA DEL REY, CA 90292 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/14/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Deputy Drilled-In Anchors | 7/20/2022 | Conditional Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 7/21/2022 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Rough | 7/21/2022 | Partial Approval | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Green Building Rough | 8/4/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Verify Sprinkler Sign Off | 8/4/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Deputy Drilled-In Anchors | 8/8/2022 | Conditional Approval | CHRISTOPHER WILSON |
| Deputy Wood Construction | 8/8/2022 | Conditional Approval | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2022 | Partial Approval | CHRISTOPHER WILSON |
| Green Building Rough | 8/9/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Verify Sprinkler Sign Off | 8/9/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| PLUMBING-Rough | 9/12/2022 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Wood Construction | 10/13/2022 | Conditional Approval | CHRISTOPHER WILSON |
| Pre-Inspection | 10/13/2022 | Partial Approval | CHRISTOPHER WILSON |
| Gas Test | 10/20/2022 | Partial Approval | CHRISTOPHER WILSON |
| PLUMBING-Rough | 10/20/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2022 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Rough | 10/24/2022 | Approved | CHRISTOPHER WILSON |
| Service/Power Release | 10/27/2022 | Approved | CHRISTOPHER WILSON |
| Rough-Elec/Plmb/HVAC | 11/10/2022 | Corrections Issued | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 11/15/2022 | Partial Approval | CHRISTOPHER WILSON |
| Shower Pan | 11/15/2022 | Partial Approval | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 11/22/2022 | Corrections Issued | CARLOS MATAMOROS |
| Green Building Rough | 11/22/2022 | Approved | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 11/22/2022 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 11/28/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 12/2/2022 | Corrections Issued | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 12/9/2022 | Approved | CHRISTOPHER WILSON |
| Green Building Rough | 12/9/2022 | Approved | CHRISTOPHER WILSON |
| HVAC-Rough | 12/9/2022 | Approved | CHRISTOPHER WILSON |
| Insulation | 12/21/2022 | Approved | CHRISTOPHER WILSON |
| Drywall Nailing | 1/3/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 2/1/2023 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 5/15/2023 | Corrections Issued | CHRISTOPHER WILSON |
| PLUMBING-Final | 5/15/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Service/Power Release | 5/15/2023 | Approved | CHRISTOPHER WILSON |
| HVAC-Final | 5/16/2023 | Approved | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 5/16/2023 | SGSOV Approved | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 5/22/2023 | Approved | CHRISTOPHER WILSON |
| Final | 5/22/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Green Building Final | 5/22/2023 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Final | 5/22/2023 | Approved | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 5/22/2023 | SGSOV Approved | CHRISTOPHER WILSON |
| Smoke Detectors | 5/22/2023 | Approved | CHRISTOPHER WILSON |
| Final | 6/13/2023 | OK to Issue CofO | CHRISTOPHER WILSON |