14720-14722 W RINALDI ST 91340
Certificate Information: 14720-14722 W RINALDI ST 91340
- Application / Permit
- 22014-20000-01958
- Plan Check / Job No.
- B22VN06278
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 8' x 5' ADDITION TO AND CONVERT THE (E) ONE CAR GARAGE INTO A (N) ACCESSORY DWELLING UNIT. ALL WORK PER ENGINEER.
- Permit Issued
- Issued on 6/6/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2022 | PINANK PATEL |
| Corrections Issued | 5/1/2022 | PINANK PATEL |
| Plan Check Approved | 5/20/2022 | PINANK PATEL |
| Building Plans Picked Up | 5/23/2022 | APPLICANT |
| Issued | 6/6/2022 | APPLICANT |
| CofO in Progress | 4/18/2023 | JENNIFER RABUCHIN |
| Permit Finaled | 4/18/2023 | MICHAEL SMITH |
| CofO Issued | 4/18/2023 | MICHAEL SMITH |
| Permit Finaled | 4/18/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 5/9/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/9/2022 | MEGAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 5/9/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 5/9/2022 | MEGAN GODINEZ |
| Grading Pre-Inspection | Cleared | 5/16/2022 | BRIAN MILLER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/24/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 7/7/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 7/12/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 7/20/2022 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 7/20/2022 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/20/2022 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 7/26/2022 | Approved | ASHLEY THOMPSON |
| HVAC-Rough | 7/26/2022 | Not Ready for Inspection | ASHLEY THOMPSON |
| PLUMBING-Rough | 7/26/2022 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 7/29/2022 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 7/29/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 7/29/2022 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/29/2022 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 8/12/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 9/23/2022 | Not Ready for Inspection | CALEB MEISTER |
| Final | 9/23/2022 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Final | 9/23/2022 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Rough | 9/23/2022 | Not Ready for Inspection | CALEB MEISTER |
| MERV13>=Final | 9/23/2022 | Not Ready for Inspection | CALEB MEISTER |
| MERV13>=Rough | 9/23/2022 | Not Ready for Inspection | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 9/23/2022 | SGSOV Not Ready | CALEB MEISTER |
| Smoke Detectors | 9/23/2022 | Approved | CALEB MEISTER |
| BUILDING-Rough-Frame | 10/5/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 10/5/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 10/5/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 10/5/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 10/5/2022 | Approved | JENNIFER RABUCHIN |
| MERV13>=Final | 10/5/2022 | Approved | JENNIFER RABUCHIN |
| MERV13>=Rough | 10/5/2022 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 10/5/2022 | SGSOV Not Ready | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 10/11/2022 | Approved | JENNIFER RABUCHIN |
| Final | 10/11/2022 | Partial Approval | JENNIFER RABUCHIN |
| HVAC-Final | 10/11/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 10/11/2022 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 10/11/2022 | SGSOV Approved | JENNIFER RABUCHIN |
| Final | 4/18/2023 | OK to Issue CofO | JENNIFER RABUCHIN |