6614-6616 N VALLEY CIRCLE BLVD 91307

Certificate Information: 6614-6616 N VALLEY CIRCLE BLVD 91307

Application / Permit
22014-20000-01939
Plan Check / Job No.
B22VN06242
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan Convert Ex. two-car garage to an ATTACHED ADU PER STATE LAW
Permit Issued
Issued on 7/24/2022
Issuing Office
Current Status
CofO Corrected on 7/12/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/25/2022 APPLICANT
Assigned to Plan Check Engineer 4/29/2022 DANIEL YIP
Corrections Issued 5/2/2022 CARLOS MONTES
Applicant returned to address corrections 6/18/2022 DANIEL YIP
Plan Check Approved 7/19/2022 DANIEL YIP
Issued 7/24/2022 APPLICANT
CofO in Progress 7/10/2023 TROY SANDERS
Re-Activate Permit 7/12/2023 JOHN JANSON
CofO Issued-Status Void 7/12/2023 JOHN JANSON
Permit Finaled-Status Void 7/12/2023 JOHN JANSON
CofO Corrected 7/12/2023 JOHN JANSON
Permit Finaled 7/12/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/4/2022 MEGAN GODINEZ
Sewer availability Cleared 5/4/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 5/5/2022 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/22/2022 Partial Approval TROY SANDERS
Deputy Reinf. Concrete 9/19/2022 Approved TROY SANDERS
Footing/Foundation/Slab 9/19/2022 Approved TROY SANDERS
PLUMBING-Rough 9/19/2022 Partial Approval TROY SANDERS
BUILDING-Rough-Frame 10/4/2022 Partial Approval TROY SANDERS
Insulation 10/4/2022 Partial Approval TROY SANDERS
Rough-Elec/Plmb/HVAC 10/4/2022 Partial Approval TROY SANDERS
Interior/Exterior Lathing 10/6/2022 Partial Inspection JOHN KIDWELL
BUILDING-Rough-Frame 11/18/2022 Approved TROY SANDERS
Green Building Rough 11/18/2022 Approved TROY SANDERS
PLUMBING-Rough 11/18/2022 Approved TROY SANDERS
Rough-Elec/Plmb/HVAC 11/18/2022 Approved TROY SANDERS
Drywall Nailing 12/8/2022 Approved TROY SANDERS
HVAC-Rough 12/8/2022 Approved TROY SANDERS
Insulation 12/8/2022 Approved TROY SANDERS
Final 2/17/2023 Corrections Issued TROY SANDERS
Footing/Foundation/Slab 2/17/2023 Approved TROY SANDERS
Green Building Final 2/17/2023 Not Ready for Inspection TROY SANDERS
SGSOV-Seismic Gas S/O Valve 2/17/2023 SGSOV Not Ready TROY SANDERS
Service/Power Release 2/17/2023 Approved TROY SANDERS
Smoke Detectors 2/17/2023 Approved TROY SANDERS
Special/Order Compliance 2/17/2023 Corrections Issued TROY SANDERS
Final 7/3/2023 Not Ready for Inspection TROY SANDERS
Green Building Final 7/3/2023 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 7/3/2023 SGSOV Approved TROY SANDERS
Final 7/10/2023 OK to Issue CofO TROY SANDERS