15722 W CASTLEWOODS DR 91403

Certificate Information: 15722 W CASTLEWOODS DR 91403

Application / Permit
22014-20000-01934
Plan Check / Job No.
B22VN06227
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
14' X 16' IRREGULAR SHAPE ADDITION TO THE (E) SFD.
Permit Issued
Issued on 8/10/2022
Issuing Office
Valley
Current Status
CofO in Progress on 1/2/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/25/2022 APPLICANT
Assigned to Plan Check Engineer 4/27/2022 SERGIO MUNIZ
Corrections Issued 5/1/2022 SERGIO MUNIZ
Applicant returned to address corrections 5/26/2022 SERGIO MUNIZ
Applicant returned to address corrections 6/9/2022 SERGIO MUNIZ
Plan Check Approved 7/27/2022 SERGIO MUNIZ
Building Plans Picked Up 8/1/2022 APPLICANT
Issued 8/10/2022 APPLICANT
CofO in Progress 8/10/2023 VINCENT HANLEY
No Progress 1/2/2025 SEAN WIRCH
CofO in Progress 1/2/2025 SEAN WIRCH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/27/2022 ROMAN GUTIERREZ
Grading Pre-Inspection Cleared 6/1/2022 MANUEL TEJADA
Eng Process Fee Ord 176,300 Cleared 6/8/2022 ROMAN GUTIERREZ
Public Works-Highway Ded. Cleared 6/8/2022 ROMAN GUTIERREZ
Public Works-Open Permits Cleared 6/8/2022 ROMAN GUTIERREZ
Public Works-Sewers Cleared 6/8/2022 ROMAN GUTIERREZ
ZA Case Cleared 6/13/2022 MIGUEL GAMBOA
Specific Plan Cleared 7/15/2022 OLGA AYALA

Contact Information

Contractor Owner-Builder       ,
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/23/2022 Corrections Issued VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 12/14/2022 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 12/23/2022 Approved VINCENT HANLEY
ELECTRICAL-Rough 12/23/2022 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 12/23/2022 Approved VINCENT HANLEY
Green Building Rough 12/23/2022 Approved VINCENT HANLEY
MERV13>=Rough 12/23/2022 Approved VINCENT HANLEY
Insulation 12/30/2022 Approved VINCENT HANLEY
Interior/Exterior Lathing 12/30/2022 Approved VINCENT HANLEY
ELECTRICAL-Final 8/9/2023 Approved VINCENT HANLEY
Final 8/9/2023 OK to Issue CofO VINCENT HANLEY
Footing/Foundation/Slab 8/9/2023 Approved VINCENT HANLEY
Green Building Final 8/9/2023 Approved VINCENT HANLEY
HVAC-Final 8/9/2023 Approved VINCENT HANLEY
MERV13>=Final 8/9/2023 Approved VINCENT HANLEY
PLUMBING-Final 8/9/2023 Approved VINCENT HANLEY
Smoke Detectors 8/9/2023 Approved VINCENT HANLEY