13058-13060 N NORRIS AVE 91342

Certificate Information: 13058-13060 N NORRIS AVE 91342

Application / Permit
22014-20000-01920
Plan Check / Job No.
B22VN06207
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 20'-9" X 25'-4 1/2" (537 SQ FT) ACCESSORY DWELLING UNIT ADDN TO EX 1-STORY SFD W/ ATT GARAGE PER LAMC 12.22A.33(c) & (e). ALL WORK PER WFPP.
Permit Issued
Issued on 2/24/2023
Issuing Office
Valley
Current Status
Issued on 2/24/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/25/2022 APPLICANT
Assigned to Plan Check Engineer 4/27/2022 SERGIO MUNIZ
Corrections Issued 5/1/2022 SERGIO MUNIZ
Building Plans Picked Up 5/13/2022 APPLICANT
Applicant returned to address corrections 8/23/2022 LUIS RINCON
Applicant returned to address corrections 9/26/2022 ALEC MOUSAKHANIAN
Plan Check Approved 2/6/2023 HAYATO TSUCHIYA
Issued 2/24/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/24/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 8/26/2022 ROMAN GUTIERREZ
Sewer availability Cleared 8/26/2022 ROMAN GUTIERREZ
Construction near power lines Cleared 12/22/2022 RIDWAN HARDY
Low Impact Development Cleared 1/27/2023 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 2/2/2023 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/3/2023 Not Ready for Inspection ARAM AVEDISIAN
Sewer 4/3/2023 Not Ready for Inspection ARAM AVEDISIAN
PLUMBING-Rough 4/4/2023 Partial Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 4/26/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Sewer 4/26/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 5/1/2023 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 5/8/2023 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 6/16/2023 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 6/21/2023 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Rough 6/21/2023 Corrections Issued MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 6/21/2023 Partial Approval MICHEL ABAJAN
Green Building Rough 6/21/2023 Not Ready for Inspection MICHEL ABAJAN
Sewer 6/21/2023 Approved MICHEL ABAJAN
Underground Mechanical 6/21/2023 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 7/7/2023 Approved MICHEL ABAJAN
Green Building Rough 7/7/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 7/7/2023 Approved MICHEL ABAJAN
Rough-Elec/Plmb/HVAC 7/7/2023 Partial Approval MICHEL ABAJAN
Insulation 7/14/2023 Approved MICHEL ABAJAN
Drywall Nailing 7/17/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 7/17/2023 Approved MICHEL ABAJAN
Final 3/19/2024 Corrections Issued KEVIN BERBERYAN
Green Building Final 3/19/2024 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 3/19/2024 SGSOV Not Ready KEVIN BERBERYAN
Service/Power Release 3/19/2024 Approved KEVIN BERBERYAN
Smoke Detectors 3/19/2024 Approved KEVIN BERBERYAN
Final 6/14/2024 Not Ready for Inspection KEVIN BERBERYAN
Green Building Final 6/14/2024 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 6/14/2024 SGSOV Approved KEVIN BERBERYAN