13058-13060 N NORRIS AVE 91342
Certificate Information: 13058-13060 N NORRIS AVE 91342
- Application / Permit
- 22014-20000-01920
- Plan Check / Job No.
- B22VN06207
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 20'-9" X 25'-4 1/2" (537 SQ FT) ACCESSORY DWELLING UNIT ADDN TO EX 1-STORY SFD W/ ATT GARAGE PER LAMC 12.22A.33(c) & (e). ALL WORK PER WFPP.
- Permit Issued
- Issued on 2/24/2023
- Issuing Office
- Valley
- Current Status
- Issued on 2/24/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/27/2022 | SERGIO MUNIZ |
| Corrections Issued | 5/1/2022 | SERGIO MUNIZ |
| Building Plans Picked Up | 5/13/2022 | APPLICANT |
| Applicant returned to address corrections | 8/23/2022 | LUIS RINCON |
| Applicant returned to address corrections | 9/26/2022 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 2/6/2023 | HAYATO TSUCHIYA |
| Issued | 2/24/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/24/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/26/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 8/26/2022 | ROMAN GUTIERREZ |
| Construction near power lines | Cleared | 12/22/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 1/27/2023 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 2/2/2023 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/3/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| Sewer | 4/3/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| PLUMBING-Rough | 4/4/2023 | Partial Approval | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 4/26/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Sewer | 4/26/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 5/1/2023 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 5/8/2023 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2023 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 6/21/2023 | Corrections Issued | MICHEL ABAJAN |
| ELECTRICAL-Rough | 6/21/2023 | Corrections Issued | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2023 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 6/21/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Sewer | 6/21/2023 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 6/21/2023 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 7/7/2023 | Approved | MICHEL ABAJAN |
| Green Building Rough | 7/7/2023 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 7/7/2023 | Approved | MICHEL ABAJAN |
| Rough-Elec/Plmb/HVAC | 7/7/2023 | Partial Approval | MICHEL ABAJAN |
| Insulation | 7/14/2023 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 7/17/2023 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 7/17/2023 | Approved | MICHEL ABAJAN |
| Final | 3/19/2024 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 3/19/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 3/19/2024 | SGSOV Not Ready | KEVIN BERBERYAN |
| Service/Power Release | 3/19/2024 | Approved | KEVIN BERBERYAN |
| Smoke Detectors | 3/19/2024 | Approved | KEVIN BERBERYAN |
| Final | 6/14/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Green Building Final | 6/14/2024 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 6/14/2024 | SGSOV Approved | KEVIN BERBERYAN |