3025-3027 E 8TH ST 90023

Certificate Information: 3025-3027 E 8TH ST 90023

Application / Permit
22014-20000-01904
Plan Check / Job No.
B22VN06158
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
RECONFIGURE (E) SINGLE FAMILY DWELLING W/ ATTACHED ACCESSORY DWELLING UNIT TO CREATE DUPLEX WITH ATTACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e). SEE COMMENTS.
Permit Issued
Issued on 6/7/2022
Issuing Office
Metro
Current Status
CofO Issued on 4/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/22/2022 APPLICANT
Assigned to Plan Check Engineer 4/29/2022 JEROME MAGAT PALMA
Corrections Issued 5/1/2022 JEROME MAGAT PALMA
Plan Check Approved 5/24/2022 JEROME MAGAT PALMA
Building Plans Picked Up 5/27/2022 APPLICANT
Issued 6/7/2022 APPLICANT
CofO in Progress 3/22/2023 FREDDIE RIVERA
Permit Finaled 4/6/2023 DEROLD HAUFF
CofO Issued 4/6/2023 DEROLD HAUFF
Permit Finaled 4/6/2023 DEROLD HAUFF

Permit Application Clearance Information

ZA Case Cleared 5/4/2022 DANG NGUYEN
Address approval Cleared 5/13/2022 STEVE MELGAR
Sewer availability Cleared 5/13/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 5/16/2022 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 10/19/2022 Partial Inspection FREDDIE RIVERA
Final 10/19/2022 Partial Inspection FREDDIE RIVERA
Footing/Foundation/Slab 10/19/2022 Partial Inspection FREDDIE RIVERA
Green Building Final 10/19/2022 Corrections Issued FREDDIE RIVERA
Green Building Rough 10/19/2022 Partial Inspection FREDDIE RIVERA
MERV13>=Final 10/19/2022 Partial Inspection FREDDIE RIVERA
MERV13>=Rough 10/19/2022 Partial Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 10/19/2022 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 10/19/2022 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 1/20/2023 Partial Inspection FREDDIE RIVERA
Final 1/20/2023 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 1/20/2023 Partial Inspection FREDDIE RIVERA
Green Building Final 1/20/2023 Partial Inspection FREDDIE RIVERA
Green Building Rough 1/20/2023 Partial Inspection FREDDIE RIVERA
MERV13>=Final 1/20/2023 Partial Inspection FREDDIE RIVERA
MERV13>=Rough 1/20/2023 Partial Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 1/20/2023 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 1/20/2023 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 3/10/2023 Approved FREDDIE RIVERA
Final 3/10/2023 Partial Inspection FREDDIE RIVERA
Footing/Foundation/Slab 3/10/2023 Partial Approval FREDDIE RIVERA
Green Building Final 3/10/2023 Approved FREDDIE RIVERA
Green Building Rough 3/10/2023 Approved FREDDIE RIVERA
MERV13>=Final 3/10/2023 Approved FREDDIE RIVERA
MERV13>=Rough 3/10/2023 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 3/10/2023 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 3/10/2023 Approved FREDDIE RIVERA
Final 3/22/2023 OK to Issue CofO FREDDIE RIVERA
Footing/Foundation/Slab 3/22/2023 Approved FREDDIE RIVERA