7825 N CLEON AVE 91352

Certificate Information: 7825 N CLEON AVE 91352

Application / Permit
22014-20000-01901
Plan Check / Job No.
B22VN06148
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(22) Storage Building
Work Description
PROPOSED 18'-0" x 22'-0" ADDITION OF A STORAGE TO THE (E) DETACHED GARAGE. ALL WORK DONE PER WFPP.
Permit Issued
Issued on 7/26/2022
Issuing Office
Valley
Current Status
CofO Issued on 1/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/21/2022 APPLICANT
Assigned to Plan Check Engineer 4/22/2022 SARKIS HARABEDIAN
Corrections Issued 4/23/2022 SARKIS HARABEDIAN
Building Plans Picked Up 4/25/2022 APPLICANT
Plan Check Approved 7/26/2022 SARKIS HARABEDIAN
Issued 7/26/2022 APPLICANT
CofO in Progress 1/4/2023 MATTHEW NELSON
CofO Issued 1/17/2023 MICHAEL SMITH
Permit Finaled 1/17/2023 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/25/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 5/10/2022 ROMAN GUTIERREZ
Public Works-Highway Ded. Cleared 7/22/2022 ROMAN GUTIERREZ
Public Works-Open Permits Cleared 7/22/2022 ROMAN GUTIERREZ
Public Works-Sewers Cleared 7/22/2022 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/3/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 8/9/2022 Approved CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 9/1/2022 Approved DEANDRE HOFFMAN
Green Building Rough 9/1/2022 Not Ready for Inspection DEANDRE HOFFMAN
Floor/Roof Diaphrgm/Shear Wall 9/8/2022 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 9/8/2022 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 9/23/2022 Approved CHRISTOPHER DELLEFIELD
Final 9/23/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 9/23/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Green Building Rough 9/23/2022 Approved CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 9/23/2022 SGSOV Approved CHRISTOPHER DELLEFIELD
Smoke Detectors 9/23/2022 Approved CHRISTOPHER DELLEFIELD
Final 9/30/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 9/30/2022 Approved CHRISTOPHER DELLEFIELD
Final 10/31/2022 Conditional Approval CHRISTOPHE COCHRAN
Final 11/30/2022 OK to Issue CofO MATTHEW NELSON