13220 W WEDDINGTON ST 91401

Certificate Information: 13220 W WEDDINGTON ST 91401

Application / Permit
22014-20000-01889
Plan Check / Job No.
B22VN06124
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL, REMOVE (E) BREEZWAY, 20'-0" X 19'-4" ADDITION TO (E) SFD & GARAGE. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 6/1/2022
Issuing Office
Current Status
CofO Issued on 4/12/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/21/2022 APPLICANT
Assigned to Plan Check Engineer 4/28/2022 ARTIN ZARUKIAN
Corrections Issued 5/2/2022 ARTIN ZARUKIAN
Plan Check Approved 6/1/2022 ARTIN ZARUKIAN
Issued 6/1/2022 APPLICANT
Building Plans Picked Up 6/6/2022 APPLICANT
CofO in Progress 2/1/2023 KIRK SANDERS
No Progress 3/6/2023 JUAN VALENZUELA
CofO in Progress 4/12/2023 RONALD MYRICK
CofO Issued 4/12/2023 RONALD MYRICK
Permit Finaled 4/12/2023 RONALD MYRICK

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/11/2022 JOSE DUARTE-DIAZ
Roof/Waste drainage to street Cleared 5/11/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 5/11/2022 JOSE DUARTE-DIAZ

Contact Information

Architect Agaian,, Raffi; Lic. No.: C32156 2234 DEL MAR ROAD UNIT # 1      MONTROSE, CA 91020
Contractor Spazio La Designs; Lic. No.: 1006766-B 10620 MAGNOLIA BLVD      NORTH HOLLYWOOD, CA 91601
Engineer Karapetian,, Arbi; Lic. No.: C79953 21520 BURBANK BLVD APT 219      WOODLAND HILLS, CA 91367

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/16/2022 Conditional Approval MATT KELLERMAN
Footing/Foundation/Slab 9/19/2022 Approved RAFAEL CORTES
Deputy Drilled-In Anchors 9/23/2022 Conditional Approval RAFAEL CORTES
BUILDING-Rough-Frame 9/26/2022 Partial Approval RAFAEL CORTES
Footing/Foundation/Slab 9/26/2022 Corrections Issued RAFAEL CORTES
PLUMBING-Rough 9/26/2022 Partial Approval RAFAEL CORTES
BUILDING-Rough-Frame 10/11/2022 Not Ready for Inspection RAFAEL CORTES
ELECTRICAL-Rough 10/11/2022 Approved RAFAEL CORTES
Green Building Rough 10/11/2022 Not Ready for Inspection RAFAEL CORTES
PLUMBING-Rough 10/11/2022 Approved RAFAEL CORTES
Interior/Exterior Lathing 10/18/2022 Approved WILLIAM WREN
Shower Pan 10/18/2022 Approved WILLIAM WREN
Insulation 10/20/2022 Approved WILLIAM WREN
BUILDING-Rough-Frame 10/24/2022 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 10/24/2022 Approved WILLIAM WREN
Green Building Rough 10/24/2022 Approved WILLIAM WREN
Interior/Exterior Lathing 10/24/2022 Approved WILLIAM WREN
Drywall Nailing 10/28/2022 Approved CHRISTOPHER DELLEFIELD
Final 1/20/2023 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 1/20/2023 Not Ready for Inspection KIRK SANDERS
Green Building Final 1/20/2023 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 1/20/2023 SGSOV Not Ready KIRK SANDERS
Smoke Detectors 1/20/2023 Approved KIRK SANDERS
Final 1/31/2023 OK to Issue CofO KIRK SANDERS
Footing/Foundation/Slab 1/31/2023 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 1/31/2023 SGSOV Approved KIRK SANDERS