9920 N PALI AVE 91042

Certificate Information: 9920 N PALI AVE 91042

Application / Permit
22014-20000-01872
Plan Check / Job No.
B22VN06029
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 10'3" X 17'7" AND CONVERT (E) 18'2" X 20'3" DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22.A33 (C) AND (D), ALL WORK PER ENGINEERING
Permit Issued
Issued on 8/4/2022
Issuing Office
Valley
Current Status
CofO Issued on 11/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/21/2022 APPLICANT
Assigned to Plan Check Engineer 5/19/2022 RARES BODEA
Corrections Issued 5/31/2022 RARES BODEA
Quality Review Completed 6/2/2022 STEVEN KIM
Building Plans Picked Up 6/6/2022 APPLICANT
Plan Check Approved 8/2/2022 RARES BODEA
Issued 8/4/2022 APPLICANT
CofO in Progress 10/30/2023 WILLIAM WREN
CofO in Progress 10/30/2023 WILLIAM WREN
Permit Finaled 11/16/2023 RUBEN SALAS
CofO Issued 11/16/2023 RUBEN SALAS
Permit Finaled 11/16/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/14/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/21/2022 CARLOS AGUILERA
Sewer availability Cleared 6/21/2022 CARLOS AGUILERA
Low Impact Development Cleared 7/15/2022 SUNG JOON WON
Grading Pre-Inspection Cleared 7/19/2022 KIRK LINKLATER
Roof/Waste drainage to street Cleared 8/2/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Baraty,, Patrick; Lic. No.: S5900 1819 SUNSHINE COURT      GLENDALE, CA 91208

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/30/2022 Approved MATTHEW NELSON
Footing/Foundation/Slab 8/30/2022 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 8/31/2022 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 9/15/2022 Approved MATTHEW NELSON
PLUMBING-Rough 9/20/2022 Approved MATTHEW NELSON
ELECTRICAL-Rough 9/28/2022 Corrections Issued MATTHEW NELSON
BUILDING-Rough-Frame 9/30/2022 Approved MATTHEW NELSON
ELECTRICAL-Rough 9/30/2022 Approved MATTHEW NELSON
Green Building Rough 9/30/2022 Approved MATTHEW NELSON
PLUMBING-Rough 9/30/2022 Approved MATTHEW NELSON
Shower Pan 9/30/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 10/19/2022 Approved MATTHEW NELSON
Drywall Nailing 10/27/2022 Approved MATTHEW NELSON
Pre-Inspection 5/31/2023 Not Ready for Inspection WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 9/12/2023 SGSOV Not Ready WILLIAM WREN
Final 10/3/2023 Corrections Issued WILLIAM WREN
Green Building Final 10/3/2023 Approved WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 10/3/2023 SGSOV Approved WILLIAM WREN
Service/Power Release 10/3/2023 Approved WILLIAM WREN
Smoke Detectors 10/3/2023 Approved WILLIAM WREN
ELECTRICAL-Final 10/10/2023 Not Ready for Inspection WILLIAM WREN
Final 10/10/2023 OK to Issue CofO WILLIAM WREN
HVAC-Final 10/10/2023 Not Ready for Inspection WILLIAM WREN
PLUMBING-Final 10/10/2023 Not Ready for Inspection WILLIAM WREN
ELECTRICAL-Final 10/16/2023 Not Ready for Inspection WILLIAM WREN
Final 10/16/2023 OK to Issue CofO WILLIAM WREN
HVAC-Final 10/16/2023 Not Ready for Inspection WILLIAM WREN
PLUMBING-Final 10/16/2023 Not Ready for Inspection WILLIAM WREN