1819 S CRESCENT HEIGHTS BLVD 90035

Certificate Information: 1819 S CRESCENT HEIGHTS BLVD 90035

Application / Permit
22014-20000-01848
Plan Check / Job No.
B22VN05933
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL, 1ST STORY 67'-4" X 20'X 1" ADDITION (E) SINGLE FAMILY DWELLING ALL WORK PER ENGINEERING
Permit Issued
Issued on 5/24/2024
Issuing Office
Valley
Current Status
CofO Issued on 7/16/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/19/2022 APPLICANT
Assigned to Plan Check Engineer 5/12/2022 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 5/16/2022 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 5/27/2022 OMID HEDAYAT
Building Plans Picked Up 6/2/2022 APPLICANT
Applicant returned to address corrections 12/21/2022 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 6/15/2023 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 10/3/2023 SEWADA ZADOORAN MILAGARDI
Issued 5/24/2024 APPLICANT
CofO in Progress 7/14/2026 DAVID WILLIAMS
Permit Finaled 7/16/2026 DEROLD HAUFF
Permit Finaled 7/16/2026 DEROLD HAUFF
CofO Issued 7/16/2026 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/25/2022 TREVOR QUAN
Sewer availability Cleared 7/25/2022 TREVOR QUAN
Low Impact Development Cleared 11/28/2022 ERNEST TSE
Roof/Waste drainage to street Cleared 10/16/2023 JEANIE LAM

Contact Information

Contractor Hernz Construction Incorporated; Lic. No.: 581129-B 8931 WOODMAN AVENUE      PACOIMA, CA 91331

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/21/2024 Approved ARTHUR NEGRETE
Footing/Foundation/Slab 6/21/2024 Approved ARTHUR NEGRETE
METHANE-Barrier 6/21/2024 Approved ARTHUR NEGRETE
METHANE-Subgrade 6/21/2024 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 7/1/2024 Partial Approval ARTHUR NEGRETE
Green Building Rough 7/1/2024 Not Ready for Inspection ARTHUR NEGRETE
METHANE-Rough 7/1/2024 Approved ARTHUR NEGRETE
PLUMBING-Rough 7/1/2024 Approved ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 7/30/2024 Approved ARTHUR NEGRETE
PLUMBING-Rough 7/30/2024 Approved ARTHUR NEGRETE
Deputy Wood Construction 7/31/2024 Conditional Approval JUSTIN HAWLEY
Interior/Exterior Lathing 8/8/2024 Approved ARTHUR NEGRETE
Shower Pan 8/8/2024 Approved ARTHUR NEGRETE
ELECTRICAL-Rough 8/16/2024 Approved ARTHUR NEGRETE
HVAC-Rough 8/16/2024 Not Ready for Inspection ARTHUR NEGRETE
PLUMBING-Rough 8/16/2024 Approved ARTHUR NEGRETE
HVAC-Rough 8/21/2024 Not Ready for Inspection ARTHUR NEGRETE
Insulation 8/23/2024 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 8/23/2024 Approved ARTHUR NEGRETE
Drywall Nailing 8/29/2024 Approved NICHOLAS LOPEZ
Green Building Rough 8/29/2024 Approved NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 12/6/2024 SGSOV Not Ready ARTHUR NEGRETE
ELECTRICAL-Final 12/10/2024 Approved ARTHUR NEGRETE
HVAC-Final 12/10/2024 Approved ARTHUR NEGRETE
PLUMBING-Final 12/10/2024 Approved ARTHUR NEGRETE
Pre-Inspection 2/5/2025 No Access for Inspection ARTHUR NEGRETE
Special/Order Compliance 2/5/2025 Partial Inspection ALEX COLIN
Excavation/Setback/Form/Re-Bar 2/6/2025 Not Ready for Inspection ARTHUR NEGRETE
BUILDING-Rough-Frame 7/15/2025 Approved ARTHUR NEGRETE
Final 7/15/2025 Partial Inspection ARTHUR NEGRETE
Green Building Final 7/15/2025 Conditional Approval ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 7/15/2025 SGSOV Approved ARTHUR NEGRETE
Smoke Detectors 7/15/2025 Approved ARTHUR NEGRETE
Final 5/13/2026 Corrections Issued DAVID WILLIAMS
Green Building Final 5/13/2026 Not Ready for Inspection DAVID WILLIAMS
Final 7/13/2026 OK to Issue CofO DAVID WILLIAMS
Green Building Final 7/13/2026 Approved DAVID WILLIAMS