17549 W LAHEY ST 91344

Certificate Information: 17549 W LAHEY ST 91344

Application / Permit
22014-20000-01839
Plan Check / Job No.
B22VN05897
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
23'-0" x 18'-1" IRREGULAR SHAPED ADDITION TO EXISTING SINGLE FAMILY DWELLING - ALL WORK PER DESIGN
Permit Issued
Issued on 9/9/2022
Issuing Office
Valley
Current Status
CofO Issued on 3/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2022 APPLICANT
Assigned to Plan Check Engineer 5/6/2022 JEROME MAGAT PALMA
Corrections Issued 5/7/2022 JEROME MAGAT PALMA
Building Plans Picked Up 5/10/2022 APPLICANT
Plan Check Approved 9/6/2022 DANIEL ABRAMYAN
Issued 9/9/2022 APPLICANT
CofO in Progress 2/23/2023 SEAN HAUPT
No Progress 2/23/2023 SEAN HAUPT
CofO in Progress 2/23/2023 SEAN HAUPT
Permit Finaled 3/7/2023 JOHN JANSON
CofO Issued 3/7/2023 JOHN JANSON
Permit Finaled 3/7/2023 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/11/2022 JOSE DUARTE-DIAZ
Roof/Waste drainage to street Cleared 5/11/2022 JOSE DUARTE-DIAZ
Public Works-Highway Ded. Cleared 5/11/2022 JOSE DUARTE-DIAZ
Public Works-Open Permits Cleared 5/11/2022 JOSE DUARTE-DIAZ
Public Works-Sewers Cleared 5/11/2022 JOSE DUARTE-DIAZ
Grading Pre-Inspection Cleared 5/12/2022 KIRK LINKLATER

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor Brewer Construction; Lic. No.: 482243-B 24307 MAGIC MOUNTAIN PRKWY #74      VALENCIA, CA 91355

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/13/2022 Conditional Approval KRISTEN CAUSEY
Excavation/Setback/Form/Re-Bar 9/16/2022 Approved DAVID SCANTLIN
Wood Frame 9/27/2022 Partial Approval DAVID SCANTLIN
BUILDING-Rough-Frame 10/13/2022 Partial Approval DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 10/13/2022 Approved DAVID SCANTLIN
Rough-Elec/Plmb/HVAC 10/13/2022 Approved DAVID SCANTLIN
Drywall Nailing 10/20/2022 Approved DAVID SCANTLIN
Insulation 10/20/2022 Approved DAVID SCANTLIN
Interior/Exterior Lathing 10/20/2022 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 2/14/2023 Approved DAVID SCANTLIN
Final 2/14/2023 Corrections Issued DAVID SCANTLIN
Footing/Foundation/Slab 2/14/2023 Approved DAVID SCANTLIN
Green Building Final 2/14/2023 Not Ready for Inspection DAVID SCANTLIN
Green Building Rough 2/14/2023 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 2/14/2023 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 2/14/2023 Approved DAVID SCANTLIN
Final 2/22/2023 OK to Issue CofO SEAN HAUPT
Green Building Final 2/22/2023 Approved SEAN HAUPT
HVAC-Final 2/22/2023 Approved SEAN HAUPT
Verify Rec and Parks Fee Memo 2/22/2023 Approved SEAN HAUPT