3666 W VALLEYBRINK ROAD 90039
Certificate Information: 3666 W VALLEYBRINK ROAD 90039
- Application / Permit
- 22014-20000-01837
- Plan Check / Job No.
- B22VN05889
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 5'-5" x 10'-5" ADDITION AT FRONT OF THE (E) SINGLE FAMILY DWELLING TO EXTEND LIVING ROOM AND CONVERT 5'-5" x 6'-1" (E)PORCH TO LIVING ROOM. ADD 8'-6" x 4'-4" PORCH. INTERIOR REMODEL TO RAISE ROOF AND RE-FRAME FROM FLAT TO VAULTED CEILING OVER THE LIVING ROOM AND DINING ROOM AND ADD A DIRECT VENT GAS FIREPLACE.
- Permit Issued
- Issued on 6/21/2022
- Issuing Office
- Metro
- Current Status
- Issued on 6/21/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2022 | SARKIS HARABEDIAN |
| Corrections Issued | 4/30/2022 | SARKIS HARABEDIAN |
| Plan Check Approved | 6/5/2022 | SARKIS HARABEDIAN |
| Building Plans Picked Up | 6/7/2022 | APPLICANT |
| Issued | 6/21/2022 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/26/2022 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 5/26/2022 | STEVE MELGAR |
Contact Information
| Contractor | Mam Enterprises Incorporated; Lic. No.: 1065646-B | 1761 N KENMORE AVENUE LOS ANGELES, CA 90027 |
| Engineer | Medina,, Ferdinand Casaclang; Lic. No.: C88007 | 1051 S HOLT AVE APT F LOS ANGELES, CA 90035 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/15/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 7/22/2022 | Approved | HAMIK HARTOUNIAN |
| Wood Frame | 8/1/2022 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 8/25/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 8/30/2022 | Approved | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 8/31/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2022 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 10/4/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 10/4/2022 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 10/4/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| MERV13>=Rough | 10/4/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 10/17/2022 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| HVAC-Rough | 11/23/2022 | Approved | JOSEPH MCGARRY |
| Wood Frame | 11/23/2022 | Approved | JOSEPH MCGARRY |
| Insulation | 11/30/2022 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 12/12/2022 | Approved | CHARLES BOGHOSKHAN |
| BUILDING-Rough-Frame | 8/14/2023 | Approved | HAMIK HARTOUNIAN |
| Final | 8/14/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 8/14/2023 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 8/14/2023 | Approved | HAMIK HARTOUNIAN |
| MERV13>=Final | 8/14/2023 | Approved | HAMIK HARTOUNIAN |
| MERV13>=Rough | 8/14/2023 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 8/14/2023 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 8/14/2023 | Approved | HAMIK HARTOUNIAN |