11588 N WELK AVE 91331

Certificate Information: 11588 N WELK AVE 91331

Application / Permit
22014-20000-01804
Plan Check / Job No.
B22VN05826
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan • CONVERT (E) 380 SF DETACHED CAR GARAGE INTO AN ACCESSORY DWELLING UNIT • 213 SF ADDITION TO (E) 280SF GARAGE to ADU conversion DETACHED ADU CHECKED PER LAMC 12.22 A.33(C) AND (D)
Permit Issued
Issued on 6/21/2022
Issuing Office
Current Status
CofO Issued on 3/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/22/2022 APPLICANT
Assigned to Plan Check Engineer 4/26/2022 SUNMIN LEE
Corrections Issued 4/28/2022 SUNMIN LEE
Applicant returned to address corrections 5/19/2022 SUNMIN LEE
Plan Check Approved 6/14/2022 SUNMIN LEE
Issued 6/21/2022 APPLICANT
CofO in Progress 12/7/2023 MICHEL ABAJAN
Permit Finaled 3/2/2024 RUBEN SALAS
CofO Issued 3/2/2024 RUBEN SALAS
Permit Finaled 3/2/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/10/2022 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 5/10/2022 MEGAN GODINEZ
Sewer availability Cleared 5/12/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 5/24/2022 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 5/24/2022 MEGAN GODINEZ
Public Works-Open Permits Cleared 5/24/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 5/24/2022 MEGAN GODINEZ
Clean Up Green Up Cleared 5/27/2022 YINGSHI HUANG
Hydrant and Access approval Cleared 6/10/2022 KURT CORRAL

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Francisco Javier; Lic. No.: C76510 2705 S FREMONT AVE APT D      ALHAMBRA, CA 91803

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/27/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 10/17/2022 Partial Approval MICHEL ABAJAN
Underground Mechanical 10/17/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 11/16/2022 Approved MICHEL ABAJAN
ELECTRICAL-Rough 11/16/2022 Approved MICHEL ABAJAN
MERV13>=Rough 11/16/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 11/16/2022 Approved MICHEL ABAJAN
Deputy Wood Construction 11/17/2022 Conditional Approval MICHAEL SMITH
HVAC-Rough 12/12/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 12/23/2022 Corrections Issued MICHEL ABAJAN
Insulation 1/4/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 1/4/2023 Approved MICHEL ABAJAN
Drywall Nailing 1/20/2023 Approved ARAM AVEDISIAN
Shower Pan 1/25/2023 Approved MATTHEW NELSON
Interior/Exterior Lathing 1/27/2023 Approved MATTHEW NELSON
HVAC-Rough 7/5/2023 Approved MICHEL ABAJAN
Pre-Inspection 9/25/2023 Approved MICHEL ABAJAN
Service/Power Release 9/29/2023 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Final 11/2/2023 Corrections Issued JENNIFER RABUCHIN
Final 11/2/2023 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 11/2/2023 Approved JENNIFER RABUCHIN
Green Building Final 11/2/2023 Approved JENNIFER RABUCHIN
HVAC-Final 11/2/2023 Corrections Issued JENNIFER RABUCHIN
MERV13>=Final 11/2/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 11/2/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 11/2/2023 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 11/2/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 12/7/2023 Approved MICHEL ABAJAN
Final 12/7/2023 OK to Issue CofO MICHEL ABAJAN
HVAC-Final 12/7/2023 Approved MICHEL ABAJAN