12465 W CLARETTA ST 91331

Certificate Information: 12465 W CLARETTA ST 91331

Application / Permit
22014-20000-01792
Plan Check / Job No.
B22VN05760
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION (24'-4" X 9'-2" ) TO THE (E) SFD FOR BEDROOMS EXPANSION. WORK PER WFPP.
Permit Issued
Issued on 7/20/2022
Issuing Office
Current Status
CofO Issued on 6/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/15/2022 APPLICANT
Assigned to Plan Check Engineer 4/18/2022 ROSENDO MEDINA
Corrections Issued 4/18/2022 ROSENDO MEDINA
Applicant returned to address corrections 6/3/2022 ROSENDO MEDINA
Plan Check Approved 7/14/2022 ROSENDO MEDINA
Building Plans Picked Up 7/18/2022 APPLICANT
Issued 7/20/2022 APPLICANT
CofO in Progress 6/11/2024 MICHEL ABAJAN
Permit Finaled 6/21/2024 RUBEN SALAS
CofO Issued 6/21/2024 RUBEN SALAS
Permit Finaled 6/21/2024 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/9/2022 CHRIS CHAHBAZ
Eng Process Fee Ord 176,300 Cleared 6/22/2022 CHRIS CHAHBAZ
Hold Cleared 2/15/2023 MARIA VENDIVIL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/15/2023 Approved MICHEL ABAJAN
Footing/Foundation/Slab 2/16/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 10/30/2023 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 10/30/2023 Partial Approval MISAEL ESPARZA
Green Building Rough 10/30/2023 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 11/3/2023 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 11/3/2023 Corrections Issued RAUL OLAGI
HVAC-Rough 11/3/2023 Approved RAUL OLAGI
BUILDING-Rough-Frame 11/16/2023 Approved MICHEL ABAJAN
ELECTRICAL-Rough 11/16/2023 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 11/16/2023 Partial Approval MICHEL ABAJAN
Green Building Rough 11/16/2023 Approved MICHEL ABAJAN
Insulation 11/17/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 11/17/2023 Approved MICHEL ABAJAN
Drywall Nailing 11/22/2023 Approved MICHEL ABAJAN
ELECTRICAL-Final 6/7/2024 Approved MICHEL ABAJAN
Final 6/7/2024 Not Ready for Inspection MICHEL ABAJAN
Green Building Final 6/7/2024 Approved MICHEL ABAJAN
HVAC-Final 6/7/2024 Approved MICHEL ABAJAN
PLUMBING-Final 6/7/2024 Corrections Issued MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 6/7/2024 SGSOV Not Ready MICHEL ABAJAN
Smoke Detectors 6/7/2024 Approved MICHEL ABAJAN
Final 6/10/2024 OK to Issue CofO MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 6/10/2024 SGSOV Approved MICHEL ABAJAN