13765 W SUNSET BLVD 90272
Certificate Information: 13765 W SUNSET BLVD 90272
- Application / Permit
- 22014-20000-01785
- Plan Check / Job No.
- B22VN05740
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND ADDITION TO (E) 1 STORY SFD FIRE SPRINKLER NFPA-13D
- Permit Issued
- Issued on 2/8/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/12/2022 | MOHAMMAD ESMAILI |
| Corrections Issued | 5/20/2022 | MOHAMMAD ESMAILI |
| Quality Review Completed | 5/25/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 5/26/2022 | APPLICANT |
| Applicant returned to address corrections | 7/18/2022 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 8/15/2022 | MOHAMMAD ESMAILI |
| Plan Check Approved | 2/3/2023 | MOHAMMAD ESMAILI |
| No Progress | 2/3/2023 | MOHAMMAD ESMAILI |
| Plan Check Approved | 2/8/2023 | MOHAMMAD ESMAILI |
| Issued | 2/8/2023 | APPLICANT |
| CofO in Progress | 3/7/2025 | JESUS RODRIGUEZ |
| Permit Finaled | 3/11/2025 | RICHARD STEINBACH |
| CofO Issued | 3/11/2025 | RICHARD STEINBACH |
| Permit Finaled | 3/11/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Miscellaneous | Cleared | 7/15/2022 | ANNA VIDAL |
| Eng Process Fee Ord 176,300 | Cleared | 11/23/2022 | JENSON LEE |
| Sewer availability | Cleared | 11/23/2022 | JENSON LEE |
| Low Impact Development | Cleared | 1/9/2023 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 1/18/2023 | JENSON LEE |
| GPI Written Notices | Cleared | 2/3/2023 | MOHAMMAD ESMAILI |
| Grading Pre-Inspection | Cleared | 2/3/2023 | MOHAMMAD ESMAILI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Aronianpour,, Eilan; Lic. No.: C88101 | 7242 JELLICO AVE LAKE BALBOA, CA 91406 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/9/2023 | Partial Approval | KENNETH NAGLE |
| Footing/Foundation/Slab | 4/14/2023 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 4/24/2023 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 5/12/2023 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Rough | 5/12/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 5/12/2023 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 5/16/2023 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 5/16/2023 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2023 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 6/5/2023 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 6/6/2023 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 6/7/2023 | Partial Approval | KEVIN SARGSYAN |
| Deputy Steel/Welding | 6/23/2023 | No Access for Inspection | KENNETH NAGLE |
| Deputy Steel/Welding | 6/28/2023 | No Access for Inspection | KENNETH NAGLE |
| Reinforced Concrete Frame | 10/19/2023 | Corrections Issued | KEVIN SARGSYAN |
| Reinforced Concrete Frame | 12/8/2023 | Approved | KEVIN SARGSYAN |
| Deputy Drilled-In Anchors | 1/11/2024 | No Access for Inspection | KENNETH NAGLE |
| Deputy Wood Construction | 1/18/2024 | Conditional Approval | KEVIN SARGSYAN |
| Deputy Wood Construction | 2/1/2024 | Conditional Approval | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 2/14/2024 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2024 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2024 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 4/12/2024 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 4/15/2024 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2024 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Rough | 4/15/2024 | Partial Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 4/15/2024 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 5/6/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Green Building Rough | 5/6/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 5/6/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 5/14/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Green Building Rough | 5/14/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 5/14/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 5/20/2024 | Partial Approval | EVAN COOPER |
| Wood Frame | 5/20/2024 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 6/4/2024 | Approved | KENNETH NAGLE |
| Green Building Rough | 6/4/2024 | Approved | KENNETH NAGLE |
| Insulation | 6/4/2024 | Approved | KENNETH NAGLE |
| Verify Sprinkler Sign Off | 6/4/2024 | Approved | KENNETH NAGLE |
| Drywall Nailing | 6/13/2024 | Approved | KEVIN SARGSYAN |
| Service/Power Release | 6/13/2024 | Corrections Issued | KEVIN SARGSYAN |
| Shower Pan | 6/13/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Shower Pan | 6/17/2024 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 12/24/2024 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Final | 12/24/2024 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Final | 12/24/2024 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Final | 1/3/2025 | Approved | EVAN COOPER |
| Gas Test | 1/28/2025 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Final | 1/28/2025 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 1/28/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| Gas Test | 2/3/2025 | Approved | JESUS RODRIGUEZ |
| Final | 2/18/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 2/18/2025 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 2/18/2025 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 2/18/2025 | Approved | JESUS RODRIGUEZ |
| Final | 3/7/2025 | OK to Issue CofO | JESUS RODRIGUEZ |
| PLUMBING-Final | 3/7/2025 | Approved | JESUS RODRIGUEZ |