13765 W SUNSET BLVD 90272

Certificate Information: 13765 W SUNSET BLVD 90272

Application / Permit
22014-20000-01785
Plan Check / Job No.
B22VN05740
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL AND ADDITION TO (E) 1 STORY SFD FIRE SPRINKLER NFPA-13D
Permit Issued
Issued on 2/8/2023
Issuing Office
Valley
Current Status
CofO Issued on 3/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/15/2022 APPLICANT
Assigned to Plan Check Engineer 5/12/2022 MOHAMMAD ESMAILI
Corrections Issued 5/20/2022 MOHAMMAD ESMAILI
Quality Review Completed 5/25/2022 OMID HEDAYAT
Building Plans Picked Up 5/26/2022 APPLICANT
Applicant returned to address corrections 7/18/2022 MOHAMMAD ESMAILI
Applicant returned to address corrections 8/15/2022 MOHAMMAD ESMAILI
Plan Check Approved 2/3/2023 MOHAMMAD ESMAILI
No Progress 2/3/2023 MOHAMMAD ESMAILI
Plan Check Approved 2/8/2023 MOHAMMAD ESMAILI
Issued 2/8/2023 APPLICANT
CofO in Progress 3/7/2025 JESUS RODRIGUEZ
Permit Finaled 3/11/2025 RICHARD STEINBACH
CofO Issued 3/11/2025 RICHARD STEINBACH
Permit Finaled 3/11/2025 RICHARD STEINBACH

Permit Application Clearance Information

Miscellaneous Cleared 7/15/2022 ANNA VIDAL
Eng Process Fee Ord 176,300 Cleared 11/23/2022 JENSON LEE
Sewer availability Cleared 11/23/2022 JENSON LEE
Low Impact Development Cleared 1/9/2023 MITESH PATEL
Roof/Waste drainage to street Cleared 1/18/2023 JENSON LEE
GPI Written Notices Cleared 2/3/2023 MOHAMMAD ESMAILI
Grading Pre-Inspection Cleared 2/3/2023 MOHAMMAD ESMAILI

Contact Information

Contractor Owner-Builder       ,
Engineer Aronianpour,, Eilan; Lic. No.: C88101 7242 JELLICO AVE      LAKE BALBOA, CA 91406

Inspector Information

KEVIN SARGSYAN, (310) 914-3889 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/9/2023 Partial Approval KENNETH NAGLE
Footing/Foundation/Slab 4/14/2023 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 4/24/2023 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 5/12/2023 Corrections Issued KEVIN SARGSYAN
Green Building Rough 5/12/2023 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 5/12/2023 Corrections Issued KEVIN SARGSYAN
BUILDING-Rough-Frame 5/16/2023 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 5/16/2023 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 5/19/2023 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 6/5/2023 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 6/6/2023 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 6/7/2023 Partial Approval KEVIN SARGSYAN
Deputy Steel/Welding 6/23/2023 No Access for Inspection KENNETH NAGLE
Deputy Steel/Welding 6/28/2023 No Access for Inspection KENNETH NAGLE
Reinforced Concrete Frame 10/19/2023 Corrections Issued KEVIN SARGSYAN
Reinforced Concrete Frame 12/8/2023 Approved KEVIN SARGSYAN
Deputy Drilled-In Anchors 1/11/2024 No Access for Inspection KENNETH NAGLE
Deputy Wood Construction 1/18/2024 Conditional Approval KEVIN SARGSYAN
Deputy Wood Construction 2/1/2024 Conditional Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 2/14/2024 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 2/14/2024 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 4/2/2024 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 4/12/2024 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 4/15/2024 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/15/2024 Corrections Issued JESUS RODRIGUEZ
HVAC-Rough 4/15/2024 Partial Approval JESUS RODRIGUEZ
PLUMBING-Rough 4/15/2024 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 5/6/2024 Not Ready for Inspection KEVIN SARGSYAN
Green Building Rough 5/6/2024 Not Ready for Inspection KEVIN SARGSYAN
Interior/Exterior Lathing 5/6/2024 Not Ready for Inspection KEVIN SARGSYAN
BUILDING-Rough-Frame 5/14/2024 Not Ready for Inspection KEVIN SARGSYAN
Green Building Rough 5/14/2024 Not Ready for Inspection KEVIN SARGSYAN
Interior/Exterior Lathing 5/14/2024 Not Ready for Inspection KEVIN SARGSYAN
Interior/Exterior Lathing 5/20/2024 Partial Approval EVAN COOPER
Wood Frame 5/20/2024 Approved EVAN COOPER
BUILDING-Rough-Frame 6/4/2024 Approved KENNETH NAGLE
Green Building Rough 6/4/2024 Approved KENNETH NAGLE
Insulation 6/4/2024 Approved KENNETH NAGLE
Verify Sprinkler Sign Off 6/4/2024 Approved KENNETH NAGLE
Drywall Nailing 6/13/2024 Approved KEVIN SARGSYAN
Service/Power Release 6/13/2024 Corrections Issued KEVIN SARGSYAN
Shower Pan 6/13/2024 Not Ready for Inspection KEVIN SARGSYAN
Shower Pan 6/17/2024 Approved KEVIN SARGSYAN
ELECTRICAL-Final 12/24/2024 Corrections Issued KEVIN SARGSYAN
HVAC-Final 12/24/2024 Corrections Issued KEVIN SARGSYAN
PLUMBING-Final 12/24/2024 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Final 1/3/2025 Approved EVAN COOPER
Gas Test 1/28/2025 Corrections Issued KEVIN SARGSYAN
HVAC-Final 1/28/2025 Approved KEVIN SARGSYAN
PLUMBING-Final 1/28/2025 Not Ready for Inspection KEVIN SARGSYAN
Gas Test 2/3/2025 Approved JESUS RODRIGUEZ
Final 2/18/2025 Corrections Issued JESUS RODRIGUEZ
Green Building Final 2/18/2025 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 2/18/2025 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 2/18/2025 Approved JESUS RODRIGUEZ
Final 3/7/2025 OK to Issue CofO JESUS RODRIGUEZ
PLUMBING-Final 3/7/2025 Approved JESUS RODRIGUEZ