8406 N TERHUNE AVE 91352

Certificate Information: 8406 N TERHUNE AVE 91352

Application / Permit
22014-20000-01776
Plan Check / Job No.
B22VN05721
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) GARAGE TO AN ACCESSORY DWELLING UNIT (ADU) PER LAMC 12.22 A.33 (c) AND (d) AND AN ADDITION OF 9'-0" x 6'-0" FULL BATHROOM TO THE ADU, AND AN ADDITION OF A 9'-0" x 6'-0", EXTERIOR ACCESS ONLY, STORAGE.
Permit Issued
Issued on 10/27/2023
Issuing Office
Valley
Current Status
CofO Issued on 5/15/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/14/2022 APPLICANT
Assigned to Plan Check Engineer 4/18/2022 LUIS RINCON
Corrections Issued 4/19/2022 LUIS RINCON
Applicant returned to address corrections 7/28/2023 HAYATO TSUCHIYA
Plan Check Approved 10/17/2023 DANIEL ABRAMYAN
Issued 10/27/2023 APPLICANT
CofO in Progress 3/24/2026 DAVID ANDERSON
Permit Finaled 5/15/2026 RUBEN SALAS
CofO Issued 5/15/2026 RUBEN SALAS
Permit Finaled 5/15/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/30/2023 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 6/30/2023 TAL SHEMEN
Roof/Waste drainage to street Cleared 6/30/2023 TAL SHEMEN
Sewer availability Cleared 6/30/2023 TAL SHEMEN
Public Works-Highway Ded. Cleared 6/30/2023 TAL SHEMEN
Public Works-Open Permits Cleared 6/30/2023 TAL SHEMEN
Public Works-Sewers Cleared 6/30/2023 TAL SHEMEN
Construction near power lines Cleared 10/10/2023 RIDWAN HARDY
Hold Cleared 10/18/2024 SANDRA SOH

Contact Information

Contractor Owner-Builder       ,
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/22/2024 Partial Approval DAVID ANDERSON
Footing/Foundation/Slab 10/24/2024 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 11/22/2024 Partial Approval DAVID ANDERSON
Green Building Rough 11/22/2024 Not Ready for Inspection DAVID ANDERSON
MERV13>=Rough 11/22/2024 Not Ready for Inspection DAVID ANDERSON
ELECTRICAL-Final 3/20/2025 Approved DAVID ANDERSON
Interior/Exterior Lathing 3/20/2025 Approved DAVID ANDERSON
PLUMBING-Rough 3/20/2025 Approved DAVID ANDERSON
ELECTRICAL-Rough 3/24/2025 Approved DAVID ANDERSON
HVAC-Rough 3/24/2025 Approved DAVID ANDERSON
Insulation 3/24/2025 Approved DAVID ANDERSON
BUILDING-Rough-Frame 3/26/2025 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 3/26/2025 Approved DAVID ANDERSON
Green Building Rough 3/26/2025 Approved DAVID ANDERSON
MERV13>=Rough 3/26/2025 Approved DAVID ANDERSON
Drywall Nailing 3/28/2025 Approved DAVID ANDERSON
Service/Power Release 8/13/2025 Corrections Issued DAVID ANDERSON
Final 9/12/2025 Corrections Issued DAVID ANDERSON
Green Building Final 9/12/2025 Not Ready for Inspection DAVID ANDERSON
MERV13>=Final 9/12/2025 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 9/12/2025 SGSOV Not Required DAVID ANDERSON
Smoke Detectors 9/12/2025 Approved DAVID ANDERSON
Final 3/23/2026 OK to Issue CofO DAVID ANDERSON
Green Building Final 3/23/2026 Approved DAVID ANDERSON