6537 W 77TH ST 90045

Certificate Information: 6537 W 77TH ST 90045

Application / Permit
22014-20000-01771
Plan Check / Job No.
B22VN05707
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
37'-3" X 13'-6" (498 SQ. FT.) IRREGULAR SHAPED ADDITION TO THE REAR OF THE (E) SFD AND INTERIOR REMODEL TO THE (E) SFD TO RECONFIGURE FLOOR PLAN. ALL WORK PER ENGINEERING
Permit Issued
Issued on 6/21/2022
Issuing Office
Current Status
CofO Issued on 4/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/14/2022 APPLICANT
Assigned to Plan Check Engineer 4/18/2022 OMAR GARNICA
Corrections Issued 4/18/2022 OMAR GARNICA
Plan Check Approved 6/13/2022 OMAR GARNICA
Building Plans Picked Up 6/15/2022 APPLICANT
Issued 6/21/2022 APPLICANT
CofO in Progress 4/14/2023 HERBERT GIRON
Permit Finaled 4/18/2023 DANIEL ORRANTE
CofO Issued 4/18/2023 DANIEL ORRANTE
Permit Finaled 4/18/2023 DANIEL ORRANTE

Permit Application Clearance Information

Sewer availability Cleared 4/23/2022 STEVEN JIN
Grading Pre-Inspection Cleared 4/28/2022 ROBERT HUGHES
Eng Process Fee Ord 176,300 Cleared 4/30/2022 STEVEN JIN
Roof/Waste drainage to street Cleared 4/30/2022 STEVEN JIN
Specific Plan Cleared 5/3/2022 FREDDY GARCIA
Construction near power lines Cleared 6/4/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Nagovitsyn,, Evgeny; Lic. No.: C93527 17436 ARMINTA ST      NORTHRIDGE, CA 91325

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/18/2022 Conditional Approval JESUS RODRIGUEZ
METHANE-Barrier 7/18/2022 Approved JESUS RODRIGUEZ
METHANE-Subgrade 7/18/2022 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 8/8/2022 Partial Approval HERBERT GIRON
Footing/Foundation/Slab 8/8/2022 Approved HERBERT GIRON
Green Building Rough 8/8/2022 Not Ready for Inspection HERBERT GIRON
METHANE-Rough 8/8/2022 Approved HERBERT GIRON
PLUMBING-Rough 8/8/2022 Partial Approval HERBERT GIRON
Insulation 8/10/2022 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 8/15/2022 Conditional Approval HERBERT GIRON
Sewer 9/26/2022 Approved HERBERT GIRON
Deputy Wood Construction 9/28/2022 Conditional Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 10/21/2022 Partial Approval HERBERT GIRON
HVAC-Rough 10/21/2022 Not Ready for Inspection HERBERT GIRON
PLUMBING-Rough 10/21/2022 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 10/28/2022 Not Ready for Inspection HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 10/28/2022 Approved HERBERT GIRON
PLUMBING-Rough 10/28/2022 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Final 11/3/2022 Not Ready for Inspection HERBERT GIRON
Interior/Exterior Lathing 11/3/2022 Partial Approval HERBERT GIRON
PLUMBING-Rough 12/2/2022 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 12/6/2022 Corrections Issued RICHARD STEINBACH
PLUMBING-Rough 12/6/2022 Conditional Approval RICHARD STEINBACH
ELECTRICAL-Rough 12/8/2022 Conditional Approval HERBERT GIRON
HVAC-Rough 12/8/2022 Corrections Issued HERBERT GIRON
PLUMBING-Rough 12/8/2022 Approved HERBERT GIRON
Wood Frame 12/8/2022 Not Ready for Inspection HERBERT GIRON
BUILDING-Rough-Frame 12/13/2022 Not Ready for Inspection HERBERT GIRON
HVAC-Rough 12/13/2022 Conditional Approval HERBERT GIRON
BUILDING-Rough-Frame 12/16/2022 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 12/20/2022 Approved HERBERT GIRON
Green Building Rough 12/20/2022 Approved HERBERT GIRON
Insulation 12/22/2022 Approved HERBERT GIRON
Drywall Nailing 12/30/2022 Approved CLAYTON GRAHAM
Interior/Exterior Lathing 1/4/2023 Partial Approval HERBERT GIRON
Shower Pan 1/4/2023 Approved HERBERT GIRON
Deputy Wood Construction 1/13/2023 Conditional Approval HERBERT GIRON
Drywall Nailing 2/6/2023 Approved HERBERT GIRON
Shower Pan 2/6/2023 Approved HERBERT GIRON
ELECTRICAL-Final 4/11/2023 Not Ready for Inspection HERBERT GIRON
Final 4/11/2023 Not Ready for Inspection HERBERT GIRON
Gas Test 4/11/2023 Approved HERBERT GIRON
Green Building Final 4/11/2023 Not Ready for Inspection HERBERT GIRON
HVAC-Final 4/11/2023 Not Ready for Inspection HERBERT GIRON
PLUMBING-Final 4/11/2023 Corrections Issued HERBERT GIRON
Smoke Detectors 4/11/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 4/13/2023 Approved HERBERT GIRON
Final 4/13/2023 OK to Issue CofO HERBERT GIRON
Green Building Final 4/13/2023 Approved HERBERT GIRON
HVAC-Final 4/13/2023 Approved HERBERT GIRON
PLUMBING-Final 4/13/2023 Approved HERBERT GIRON
Service/Power Release 4/13/2023 Approved HERBERT GIRON
Smoke Detectors 4/13/2023 Approved HERBERT GIRON