5960 N JELLICO AVE 91316
Certificate Information: 5960 N JELLICO AVE 91316
- Application / Permit
- 22014-20000-01768
- Plan Check / Job No.
- B22VN05698
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 36'-7"' X 44'-5" IRREGULAR SHAPED ADDITION AND REMODEL TO (E) SFD. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 6/8/2022
- Issuing Office
- Current Status
- CofO Issued on 4/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/12/2022 | RAPHAEL ROSAS |
| Corrections Issued | 5/18/2022 | RAPHAEL ROSAS |
| Quality Review Completed | 5/24/2022 | STEVEN KIM |
| Building Plans Picked Up | 5/24/2022 | APPLICANT |
| Plan Check Approved | 6/8/2022 | RAPHAEL ROSAS |
| Issued | 6/8/2022 | APPLICANT |
| CofO in Progress | 4/6/2023 | JON MCHUGH |
| Permit Finaled | 4/13/2023 | JOHN JANSON |
| CofO Issued | 4/13/2023 | JOHN JANSON |
| Permit Finaled | 4/13/2023 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/17/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 5/17/2022 | CARLOS AGUILERA |
| ZI | Cleared | 5/20/2022 | STEVEN WECHSLER |
| Low Impact Development | Cleared | 6/2/2022 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 6/2/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/2/2022 | Partial Approval | SEAN HAUPT |
| Deputy Drilled-In Anchors | 8/8/2022 | Partial Approval | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 8/11/2022 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 8/11/2022 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2022 | Not Ready for Inspection | SEAN HAUPT |
| PLUMBING-Rough | 8/22/2022 | Not Ready for Inspection | SEAN HAUPT |
| PLUMBING-Rough | 8/26/2022 | Partial Approval | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 10/24/2022 | Not Ready for Inspection | SEAN HAUPT |
| HVAC-Rough | 10/24/2022 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 10/24/2022 | Approved | SEAN HAUPT |
| Wood Frame | 10/24/2022 | Not Ready for Inspection | SEAN HAUPT |
| BUILDING-Rough-Frame | 10/31/2022 | Corrections Issued | SEAN HAUPT |
| ELECTRICAL-Rough | 10/31/2022 | Not Ready for Inspection | SEAN HAUPT |
| Green Building Rough | 10/31/2022 | Not Ready for Inspection | SEAN HAUPT |
| HVAC-Rough | 10/31/2022 | Not Ready for Inspection | SEAN HAUPT |
| PLUMBING-Rough | 10/31/2022 | Corrections Issued | SEAN HAUPT |
| PLUMBING-Rough | 11/3/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 11/8/2022 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 11/9/2022 | Approved | SEAN HAUPT |
| Green Building Rough | 11/9/2022 | Approved | SEAN HAUPT |
| HVAC-Rough | 11/9/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 11/9/2022 | Approved | SEAN HAUPT |
| Insulation | 11/16/2022 | Approved | MORRIS JACKSON |
| Drywall Nailing | 11/22/2022 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 11/22/2022 | Approved | KRISTEN CAUSEY |
| Shower Pan | 11/22/2022 | Approved | KRISTEN CAUSEY |
| Final | 3/30/2023 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 3/30/2023 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 3/30/2023 | SGSOV Approved | SEAN HAUPT |
| Smoke Detectors | 3/30/2023 | Approved | SEAN HAUPT |
| Special/Order Compliance | 3/30/2023 | Partial Inspection | MORRIS JACKSON |
| Final | 4/5/2023 | Partial Approval | JON MCHUGH |