19325 W FRIAR ST 91335
Certificate Information: 19325 W FRIAR ST 91335
- Application / Permit
- 22014-20000-01766
- Plan Check / Job No.
- B22VN05697
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY ACCESSORY DWELING UNIT ATTACHED TO (E) GARAGE per LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 12/7/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/12/2022 | MOHAMMAD ESMAILI |
| Corrections Issued | 5/20/2022 | MOHAMMAD ESMAILI |
| Quality Review Completed | 5/25/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 5/26/2022 | APPLICANT |
| Plan Check Approved | 11/9/2022 | MOHAMMAD ESMAILI |
| Issued | 12/7/2022 | APPLICANT |
| CofO in Progress | 9/5/2024 | ALEXANDER HANDY |
| CofO Issued | 11/19/2024 | JOHN JANSON |
| Permit Finaled | 11/19/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/2/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 7/6/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 7/6/2022 | DAGOVERTO GUERRERO |
| ZI | Cleared | 7/8/2022 | STEVEN WECHSLER |
| Construction near power lines | Cleared | 9/29/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 10/28/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 10/28/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chatsky,, German; Lic. No.: C84153 | 3876 HUNTERS GROVE CT MOORPARK, CA 93021 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/4/2023 | Approved | HORACE FULTZ |
| Footing/Foundation/Slab | 4/17/2023 | Approved | ALEXANDER HANDY |
| Underground Mechanical | 7/3/2023 | No Access for Inspection | JEFFREY PARD |
| Sewer | 7/6/2023 | Approved | JOHN KIDWELL |
| Underground Mechanical | 7/6/2023 | Partial Approval | JOHN KIDWELL |
| Underground Mechanical | 7/20/2023 | Partial Approval | ALEXANDER HANDY |
| Underground Mechanical | 8/3/2023 | Approved | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2023 | Corrections Issued | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2023 | Partial Approval | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2023 | Corrections Issued | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 10/27/2023 | Corrections Issued | MORRIS JACKSON |
| ELECTRICAL-Rough | 10/27/2023 | Approved | MORRIS JACKSON |
| Green Building Rough | 10/27/2023 | Not Ready for Inspection | MORRIS JACKSON |
| HVAC-Rough | 10/27/2023 | Not Ready for Inspection | MORRIS JACKSON |
| PLUMBING-Rough | 10/27/2023 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 11/2/2023 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 11/2/2023 | Not Ready for Inspection | JOHN KIDWELL |
| HVAC-Rough | 11/2/2023 | Not Ready for Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 11/22/2023 | Approved | ALEXANDER HANDY |
| Green Building Rough | 11/22/2023 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 11/22/2023 | Partial Approval | ALEXANDER HANDY |
| Insulation | 12/6/2023 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Rough | 12/18/2023 | Not Ready for Inspection | MORRIS JACKSON |
| Drywall Nailing | 12/19/2023 | Approved | MORRIS JACKSON |
| Final | 4/16/2024 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 4/16/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 4/16/2024 | SGSOV Not Ready | ALEXANDER HANDY |
| Smoke Detectors | 4/16/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| Final | 4/23/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| Green Building Final | 4/23/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 4/23/2024 | SGSOV Not Ready | ALEXANDER HANDY |
| Smoke Detectors | 4/23/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| Final | 5/14/2024 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 5/14/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 5/14/2024 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 5/14/2024 | Approved | ALEXANDER HANDY |
| Final | 6/14/2024 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 6/14/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| Service/Power Release | 6/14/2024 | Approved | ALEXANDER HANDY |
| Final | 6/24/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| ELECTRICAL-Final | 9/4/2024 | Approved | ALEXANDER HANDY |
| Final | 9/4/2024 | OK to Issue CofO | ALEXANDER HANDY |
| Green Building Final | 9/4/2024 | Approved | ALEXANDER HANDY |
| HVAC-Final | 9/4/2024 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 9/4/2024 | Approved | ALEXANDER HANDY |