7303 N SHOUP AVE 91307

Certificate Information: 7303 N SHOUP AVE 91307

Application / Permit
22014-20000-01738
Plan Check / Job No.
B22VN05631
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE EX. 21' x 21'6" GARAGE AND ADD 30'3" x 15'2" ADDITION FOR ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 6/29/2022
Issuing Office
Valley
Current Status
CofO Issued on 4/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/13/2022 APPLICANT
Assigned to Plan Check Engineer 4/15/2022 JEFFREY TANGONAN
Corrections Issued 4/16/2022 JEFFREY TANGONAN
Plan Check Approved 6/22/2022 JEFFREY TANGONAN
Building Plans Picked Up 6/23/2022 APPLICANT
Issued 6/29/2022 APPLICANT
CofO in Progress 4/3/2023 KRISTEN BEVERIDGE
CofO Issued 4/21/2023 JOHN JANSON
Permit Finaled 4/21/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/4/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 5/4/2022 ROMAN GUTIERREZ
Roof/Waste drainage to street Cleared 5/4/2022 ROMAN GUTIERREZ
Sewer availability Cleared 5/10/2022 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Adams,, Robert Charles; Lic. No.: C21234 22129 BRYANT STREET      CANOGA PARK, CA 91304

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/12/2022 Partial Approval DAVID SANDOVAL
Deputy Drilled-In Anchors 9/16/2022 Conditional Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 9/16/2022 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 9/28/2022 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 10/24/2022 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 10/24/2022 Approved CHRIS CHRISTENSEN
Green Building Rough 10/24/2022 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Rough 10/24/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 10/24/2022 Approved CHRIS CHRISTENSEN
Sewer 10/24/2022 Approved CHRIS CHRISTENSEN
Shower Pan 10/24/2022 Approved CHRIS CHRISTENSEN
Underground Mechanical 10/24/2022 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 10/31/2022 Approved CHRIS CHRISTENSEN
Green Building Rough 10/31/2022 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 10/31/2022 Partial Approval CHRIS CHRISTENSEN
Shower Pan 10/31/2022 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 11/1/2022 Partial Approval JUSTIN HAWLEY
Shower Pan 11/1/2022 Approved JUSTIN HAWLEY
Drywall Nailing 11/7/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Final 11/7/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Final 11/7/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Insulation 11/7/2022 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 11/7/2022 Partial Approval CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 11/7/2022 SGSOV Not Ready CHRIS CHRISTENSEN
Service/Power Release 11/7/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Smoke Detectors 11/7/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Drywall Nailing 11/14/2022 Approved JUSTIN HAWLEY
Final 1/3/2023 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 1/3/2023 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 1/3/2023 SGSOV Not Ready CHRIS CHRISTENSEN
Smoke Detectors 1/3/2023 Approved CHRIS CHRISTENSEN
Final 1/9/2023 No Access for Inspection KRISTEN CAUSEY
Green Building Final 1/9/2023 No Access for Inspection KRISTEN CAUSEY
SGSOV-Seismic Gas S/O Valve 1/9/2023 SGSOV Not Ready KRISTEN CAUSEY
Final 1/17/2023 Not Ready for Inspection KRISTEN CAUSEY
Green Building Final 1/17/2023 Not Ready for Inspection KRISTEN CAUSEY
SGSOV-Seismic Gas S/O Valve 1/17/2023 SGSOV Not Ready KRISTEN CAUSEY
Final 1/27/2023 Conditional Approval KRISTEN CAUSEY
Green Building Final 1/27/2023 Conditional Approval KRISTEN CAUSEY
SGSOV-Seismic Gas S/O Valve 1/27/2023 SGSOV Approved KRISTEN CAUSEY
Final 2/8/2023 Not Ready for Inspection KRISTEN CAUSEY
Green Building Final 2/8/2023 Not Ready for Inspection KRISTEN CAUSEY
Final 3/8/2023 Not Ready for Inspection KRISTEN CAUSEY
Green Building Final 3/8/2023 Not Ready for Inspection KRISTEN CAUSEY
Green Building Final 3/23/2023 Approved KRISTEN CAUSEY
Final 3/28/2023 OK to Issue CofO KRISTEN CAUSEY