Work Description
INTERIOR REMODEL TO ADD NEW STAIRWAY FOR NEW ROOFTOP DECK TO AN (E) 2-STORY SINGLE FAMILY DWELLING. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 7/11/2022
Issuing Office
Current Status
CofO Issued on 5/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/12/2022 APPLICANT
Assigned to Plan Check Engineer 5/12/2022 COLIN LOREDO
Corrections Issued 5/17/2022 COLIN LOREDO
Quality Review Completed 5/25/2022 OMID HEDAYAT
Building Plans Picked Up 5/25/2022 APPLICANT
Plan Check Approved 6/30/2022 COLIN LOREDO
Issued 7/11/2022 APPLICANT
CofO in Progress 5/11/2023 JOAQUIN GREENOUGH
CofO Issued 5/19/2023 DEROLD HAUFF
Permit Finaled 5/19/2023 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/31/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 6/8/2022 CINDY QI

Contact Information

Contractor Sl Usa Group Inc; Lic. No.: 1050905-B 5042 WILSHIRE BLVD STE 250      LOS ANGELES, CA 90036
Engineer Phillips,, Craig; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/7/2022 Corrections Issued JOAQUIN GREENOUGH
Deputy Drilled-In Anchors 10/4/2022 Conditional Approval JOAQUIN GREENOUGH
Pre-Inspection 11/3/2022 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 11/8/2022 Approved JOAQUIN GREENOUGH
METHANE-Barrier 11/8/2022 Approved JOAQUIN GREENOUGH
METHANE-Subgrade 11/8/2022 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 11/23/2022 Corrections Issued BRIAN SULLIVAN
Green Building Rough 11/23/2022 Not Ready for Inspection BRIAN SULLIVAN
METHANE-Rough 11/23/2022 Approved BRIAN SULLIVAN
Wood Frame 11/23/2022 Partial Approval BRIAN SULLIVAN
BUILDING-Rough-Frame 1/31/2023 Corrections Issued RAUL BARAJAS
Green Building Rough 1/31/2023 Not Ready for Inspection RAUL BARAJAS
BUILDING-Rough-Frame 2/9/2023 Approved RAUL BARAJAS
Green Building Rough 2/9/2023 Approved RAUL BARAJAS
Deputy Wood Construction 2/14/2023 Conditional Approval RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 2/14/2023 Approved STUART CHAPMAN
Drywall Nailing 2/21/2023 Approved JOAQUIN GREENOUGH
Wood Frame 4/15/2023 Partial Approval JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 5/3/2023 SGSOV Not Ready JOAQUIN GREENOUGH
Final 5/10/2023 Conditional Approval BRIAN SULLIVAN
Green Building Final 5/10/2023 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 5/10/2023 SGSOV Approved BRIAN SULLIVAN
Smoke Detectors 5/10/2023 Approved BRIAN SULLIVAN
Final 5/11/2023 OK to Issue CofO JOAQUIN GREENOUGH