6126 N ALONZO AVE 91316

Certificate Information: 6126 N ALONZO AVE 91316

Application / Permit
22014-20000-01694
Plan Check / Job No.
B22VN05501
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED IRR SHAPED 25'9" x 23'6" DINING RM ADDN. EXPAND & REMODEL EX KITCHEN. CONVERT EX CLOSET INTO 1/2 BATH. AND REMODEL EX BATHRMS PER PLAN. NEW WASHER/DRYER RECESSED INTO EX GARAGE. ALL WORK PER ENGINEERING
Permit Issued
Issued on 10/13/2022
Issuing Office
Valley
Current Status
CofO Issued on 8/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/11/2022 APPLICANT
Assigned to Plan Check Engineer 4/12/2022 LUISANGEL VALENZUELA
Corrections Issued 4/12/2022 LUISANGEL VALENZUELA
Building Plans Picked Up 4/13/2022 APPLICANT
Applicant returned to address corrections 10/11/2022 HAYATO TSUCHIYA
Issued 10/13/2022 APPLICANT
CofO in Progress 8/9/2023 JON MCHUGH
Permit Finaled 8/14/2023 DANIEL ORRANTE
CofO Issued 8/14/2023 DANIEL ORRANTE
Permit Finaled 8/14/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/29/2022 JOSE DUARTE-DIAZ
Low Impact Development Cleared 9/29/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 9/29/2022 JOSE DUARTE-DIAZ
Public Works-Highway Ded. Cleared 9/29/2022 JOSE DUARTE-DIAZ
Public Works-Sewers Cleared 9/29/2022 JOSE DUARTE-DIAZ
Public Works-Open Permits Cleared 9/29/2022 JOSE DUARTE-DIAZ

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor Owner-Builder       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/21/2022 Corrections Issued SEAN WIRCH
Excavation/Setback/Form/Re-Bar 11/30/2022 Corrections Issued SEAN HAUPT
Footing/Foundation/Slab 11/30/2022 Not Ready for Inspection SEAN HAUPT
BUILDING-Rough-Frame 12/2/2022 Off-Hour Fees Due
ELECTRICAL-Final 12/2/2022 Off-Hour Fees Due
Green Building Rough 12/2/2022 Off-Hour Fees Due
Reinforced Concrete Frame 12/2/2022 Off-Hour Fees Due
Service/Power Release 12/2/2022 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 12/7/2022 Corrections Issued JON MCHUGH
Footing/Foundation/Slab 12/7/2022 Not Ready for Inspection JON MCHUGH
Footing/Foundation/Slab 12/9/2022 Corrections Issued JON MCHUGH
Footing/Foundation/Slab 2/21/2023 Approved JON MCHUGH
BUILDING-Rough-Frame 3/10/2023 Partial Approval JON MCHUGH
Green Building Rough 3/10/2023 Not Ready for Inspection JON MCHUGH
Deputy Wood Construction 3/24/2023 Partial Approval SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 3/28/2023 Partial Approval JON MCHUGH
Green Building Rough 3/28/2023 Not Ready for Inspection JON MCHUGH
ELECTRICAL-Rough 4/26/2023 Not Ready for Inspection JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 4/26/2023 Partial Approval JON MCHUGH
HVAC-Rough 4/26/2023 Not Ready for Inspection JON MCHUGH
BUILDING-Rough-Frame 5/3/2023 Not Ready for Inspection JON MCHUGH
Green Building Rough 5/3/2023 Approved JON MCHUGH
Wood Frame 5/3/2023 Partial Approval JON MCHUGH
BUILDING-Rough-Frame 5/9/2023 Approved JON MCHUGH
BUILDING-Rough-Frame 5/12/2023 Approved JON MCHUGH
Drywall Nailing 5/12/2023 Approved JON MCHUGH
Final 5/12/2023 Corrections Issued JON MCHUGH
Final 7/26/2023 Not Ready for Inspection JEFFREY PARD
Green Building Final 7/26/2023 Not Ready for Inspection JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 7/26/2023 SGSOV Approved JEFFREY PARD
Smoke Detectors 7/26/2023 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Final 8/9/2023 Approved JON MCHUGH
Final 8/9/2023 OK to Issue CofO JON MCHUGH
Green Building Final 8/9/2023 Approved JON MCHUGH
HVAC-Final 8/9/2023 Approved JON MCHUGH
PLUMBING-Final 8/9/2023 Approved JON MCHUGH
Smoke Detectors 8/9/2023 Approved JON MCHUGH