6914 3/4 S MAIN ST 90003
Certificate Information: 6914 3/4 S MAIN ST 90003
- Application / Permit
- 22014-20000-01669
- Plan Check / Job No.
- B22VN05412
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 18' X 20' PORTION OF (E) DETACHED 2-CAR GARAGE TO ACCESSORY DWELLING UNIT AND ADD 20' X 5' 6" TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d). ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 9/2/2022
- Issuing Office
- Metro
- Current Status
- Issued on 9/2/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/13/2022 | LUIS RINCON |
| Corrections Issued | 4/16/2022 | LUIS RINCON |
| Building Plans Picked Up | 4/18/2022 | APPLICANT |
| Applicant returned to address corrections | 8/12/2022 | SERGIO MUNIZ |
| Plan Check Approved | 8/26/2022 | GURUNATH NESARAJAH |
| Issued | 9/2/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/21/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 4/21/2022 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 4/21/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 4/21/2022 | JEANETTE VONG |
| Community Plan Implem. Overlay | Cleared | 7/26/2022 | HELEN JADALI |
| ZI | Cleared | 7/26/2022 | HELEN JADALI |
| Redevelopment Project Area | Cleared | 8/3/2022 | DAVID URITA |
| ZI | Cleared | 8/3/2022 | DAVID URITA |
Contact Information
| No Data Available. |
Inspector Information
| ALFREDO LOPEZ, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/23/2023 | Approved | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 6/8/2023 | Partial Approval | JAMES POWERS |
| Wood Frame | 7/7/2023 | Partial Approval | JAMES POWERS |
| Wood Frame | 3/28/2024 | Partial Approval | JAMES POWERS |
| Interior/Exterior Lathing | 4/10/2024 | Approved | JAMES POWERS |
| Insulation | 5/14/2024 | Approved | JAMES POWERS |
| Drywall Nailing | 5/16/2024 | Approved | JAMES POWERS |
| BUILDING-Rough-Frame | 11/6/2024 | Approved | JAMES POWERS |
| Final | 11/6/2024 | Not Ready for Inspection | JAMES POWERS |
| Green Building Final | 11/6/2024 | Approved | JAMES POWERS |
| Green Building Rough | 11/6/2024 | Approved | JAMES POWERS |
| SGSOV-Seismic Gas S/O Valve | 11/6/2024 | SGSOV Not Ready | JAMES POWERS |
| Smoke Detectors | 11/6/2024 | Not Ready for Inspection | JAMES POWERS |
| Final | 11/20/2024 | OK for TCO | JAMES POWERS |
| SGSOV-Seismic Gas S/O Valve | 11/20/2024 | SGSOV No Gas | JAMES POWERS |
| Smoke Detectors | 11/20/2024 | Approved | JAMES POWERS |