8201 N ENCINO AVE 91325

Certificate Information: 8201 N ENCINO AVE 91325

Application / Permit
22014-20000-01657
Plan Check / Job No.
B22VN05380
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
16'-0" X 8'-6" ADDITION OF A BATHROOM AND WALK IN CLOSET TO THE (E) SFD AND INTERIOR REMODEL TO THE (E) BATHROOM AND CLOSET PER WFPP.
Permit Issued
Issued on 5/2/2022
Issuing Office
Current Status
CofO Issued on 10/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/8/2022 APPLICANT
Assigned to Plan Check Engineer 4/13/2022 ARTIN ZARUKIAN
Corrections Issued 4/18/2022 ARTIN ZARUKIAN
Plan Check Approved 5/2/2022 ARTIN ZARUKIAN
Issued 5/2/2022 APPLICANT
Building Plans Picked Up 5/6/2022 APPLICANT
CofO in Progress 10/25/2022 RAUL OLAGI
Permit Finaled 10/29/2022 MICHAEL SMITH
CofO Issued 10/29/2022 MICHAEL SMITH
Permit Finaled 10/29/2022 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/20/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 4/21/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/7/2022 Conditional Approval JAVIER RAMOS JR
PLUMBING-Rough 6/10/2022 Corrections Issued DEANDRE HOFFMAN
PLUMBING-Rough 6/14/2022 Corrections Issued ALAN MORELOS
Footing/Foundation/Slab 6/20/2022 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 8/3/2022 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 8/3/2022 Corrections Issued RAUL OLAGI
PLUMBING-Rough 8/3/2022 Partial Approval RAUL OLAGI
Deputy Drilled-In Anchors 8/5/2022 Conditional Approval DEANDRE HOFFMAN
BUILDING-Rough-Frame 8/9/2022 Approved RAUL OLAGI
Rough-Elec/Plmb/HVAC 8/9/2022 Partial Approval RAUL OLAGI
Insulation 8/19/2022 Partial Approval RAUL OLAGI
Interior/Exterior Lathing 8/19/2022 Partial Inspection RAUL OLAGI
Drywall Nailing 8/26/2022 Partial Approval RAUL OLAGI
Green Building Rough 8/26/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 8/26/2022 Partial Approval RAUL OLAGI
Shower Pan 8/26/2022 Partial Approval RAUL OLAGI
PLUMBING-Rough 9/23/2022 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 9/29/2022 Approved RAUL OLAGI
Insulation 9/29/2022 Approved RAUL OLAGI
Rough-Elec/Plmb/HVAC 9/29/2022 Approved RAUL OLAGI
Drywall Nailing 10/5/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 10/5/2022 Approved RAUL OLAGI
Shower Pan 10/5/2022 Approved RAUL OLAGI
Final 10/24/2022 Corrections Issued RAUL OLAGI
Green Building Final 10/24/2022 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 10/24/2022 SGSOV Approved RAUL OLAGI
Smoke Detectors 10/24/2022 Approved RAUL OLAGI
Final 10/25/2022 OK to Issue CofO RAUL OLAGI