8201 N ENCINO AVE 91325
Certificate Information: 8201 N ENCINO AVE 91325
- Application / Permit
- 22014-20000-01657
- Plan Check / Job No.
- B22VN05380
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 16'-0" X 8'-6" ADDITION OF A BATHROOM AND WALK IN CLOSET TO THE (E) SFD AND INTERIOR REMODEL TO THE (E) BATHROOM AND CLOSET PER WFPP.
- Permit Issued
- Issued on 5/2/2022
- Issuing Office
- Current Status
- CofO Issued on 10/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/13/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 4/18/2022 | ARTIN ZARUKIAN |
| Plan Check Approved | 5/2/2022 | ARTIN ZARUKIAN |
| Issued | 5/2/2022 | APPLICANT |
| Building Plans Picked Up | 5/6/2022 | APPLICANT |
| CofO in Progress | 10/25/2022 | RAUL OLAGI |
| Permit Finaled | 10/29/2022 | MICHAEL SMITH |
| CofO Issued | 10/29/2022 | MICHAEL SMITH |
| Permit Finaled | 10/29/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/20/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/21/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/7/2022 | Conditional Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 6/10/2022 | Corrections Issued | DEANDRE HOFFMAN |
| PLUMBING-Rough | 6/14/2022 | Corrections Issued | ALAN MORELOS |
| Footing/Foundation/Slab | 6/20/2022 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 8/3/2022 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 8/3/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 8/3/2022 | Partial Approval | RAUL OLAGI |
| Deputy Drilled-In Anchors | 8/5/2022 | Conditional Approval | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 8/9/2022 | Approved | RAUL OLAGI |
| Rough-Elec/Plmb/HVAC | 8/9/2022 | Partial Approval | RAUL OLAGI |
| Insulation | 8/19/2022 | Partial Approval | RAUL OLAGI |
| Interior/Exterior Lathing | 8/19/2022 | Partial Inspection | RAUL OLAGI |
| Drywall Nailing | 8/26/2022 | Partial Approval | RAUL OLAGI |
| Green Building Rough | 8/26/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 8/26/2022 | Partial Approval | RAUL OLAGI |
| Shower Pan | 8/26/2022 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 9/23/2022 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 9/29/2022 | Approved | RAUL OLAGI |
| Insulation | 9/29/2022 | Approved | RAUL OLAGI |
| Rough-Elec/Plmb/HVAC | 9/29/2022 | Approved | RAUL OLAGI |
| Drywall Nailing | 10/5/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 10/5/2022 | Approved | RAUL OLAGI |
| Shower Pan | 10/5/2022 | Approved | RAUL OLAGI |
| Final | 10/24/2022 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 10/24/2022 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 10/24/2022 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 10/24/2022 | Approved | RAUL OLAGI |
| Final | 10/25/2022 | OK to Issue CofO | RAUL OLAGI |