20459 W LIVERPOOL WAY 91326

Certificate Information: 20459 W LIVERPOOL WAY 91326

Application / Permit
22014-20000-01656
Plan Check / Job No.
B22VN05378
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD A 2-STORY ELEVATOR HOIST WAY TO (E) SFD AND ELVATOR EQUIPMENT ROOM TO GARAGE
Permit Issued
Issued on 8/25/2022
Issuing Office
Valley
Current Status
CofO Issued on 9/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/28/2022 APPLICANT
Assigned to Plan Check Engineer 5/26/2022 MOHAMMAD ESMAILI
Corrections Issued 6/3/2022 MOHAMMAD ESMAILI
Quality Review Completed 6/3/2022 OMID HEDAYAT
Building Plans Picked Up 6/8/2022 APPLICANT
Plan Check Approved 8/11/2022 MOHAMMAD ESMAILI
Issued 8/25/2022 APPLICANT
CofO in Progress 9/15/2023 STEVEN BACK
Permit Finaled 9/22/2023 JOHN JANSON
CofO Issued 9/22/2023 JOHN JANSON
Permit Finaled 9/22/2023 JOHN JANSON

Permit Application Clearance Information

"T" removal Cleared 6/13/2022 DANG NGUYEN
Eng Process Fee Ord 176,300 Cleared 6/13/2022 CARLOS AGUILERA
Miscellaneous Cleared 6/13/2022 DANG NGUYEN
Miscellaneous Cleared 6/13/2022 DANG NGUYEN
Roof/Waste drainage to street Cleared 6/13/2022 CARLOS AGUILERA
Specific Plan Cleared 6/13/2022 DANG NGUYEN
ZA Case Cleared 6/13/2022 DANG NGUYEN
ZA Case Cleared 6/13/2022 DANG NGUYEN
ZI Cleared 6/13/2022 DANG NGUYEN
Grading Pre-Inspection Cleared 6/22/2022 KIRK LINKLATER
Distance to fire station Cleared 7/12/2022 LAVEON RIDER
Hydrant and Access approval Cleared 7/12/2022 LAVEON RIDER

Contact Information

Contractor Mulick Construction And Design Inc; Lic. No.: 372231-B 1476 DORSET AVENUE      THOUSAND OAKS, CA 91360

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/2/2022 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 10/6/2022 Approved DAVID SCANTLIN
ELECTRICAL-Rough 10/6/2022 Approved DAVID SCANTLIN
Insulation 10/6/2022 Approved DAVID SCANTLIN
Drywall Nailing 10/14/2022 Approved JEFFREY PARD
Interior/Exterior Lathing 10/14/2022 Approved JEFFREY PARD
BUILDING-Rough-Frame 12/8/2022 Approved DAVID SCANTLIN
Final 12/8/2022 Corrections Issued DAVID SCANTLIN
Green Building Final 12/8/2022 Approved DAVID SCANTLIN
Green Building Rough 12/8/2022 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 12/8/2022 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 12/8/2022 Approved DAVID SCANTLIN
Final 9/15/2023 OK to Issue CofO STEVEN BACK