21901 W GALENDO PL 91364

Certificate Information: 21901 W GALENDO PL 91364

Application / Permit
22014-20000-01654
Plan Check / Job No.
B22VN05365
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO BOTH SIDES AND CONVERT (E) GARAGE TO IRR. SHAPED DET. 26'-1" x 40'-6" ONE-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 8/8/2022
Issuing Office
Valley
Current Status
CofO Issued on 4/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/8/2022 APPLICANT
Assigned to Plan Check Engineer 5/5/2022 SEAN SHAHMIRI
Corrections Issued 5/10/2022 SEAN SHAHMIRI
Quality Review Completed 5/18/2022 OMID HEDAYAT
Building Plans Picked Up 5/19/2022 APPLICANT
Applicant returned to address corrections 6/16/2022 SEAN SHAHMIRI
Plan Check Approved 8/8/2022 SEAN SHAHMIRI
Issued 8/8/2022 APPLICANT
CofO in Progress 3/29/2023 PETER FOLLING
Permit Finaled 4/3/2023 JOHN JANSON
CofO Issued 4/3/2023 JOHN JANSON
Permit Finaled 4/3/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/17/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 5/17/2022 ROMAN GUTIERREZ
Roof/Waste drainage to street Cleared 5/17/2022 ROMAN GUTIERREZ
Sewer availability Cleared 5/17/2022 ROMAN GUTIERREZ
Specific Plan Cleared 5/17/2022 OLGA AYALA
Specific Plan Cleared 5/17/2022 OLGA AYALA
Public Works-Highway Ded. Cleared 5/17/2022 ROMAN GUTIERREZ
Public Works-Open Permits Cleared 5/17/2022 ROMAN GUTIERREZ
Public Works-Sewers Cleared 5/17/2022 ROMAN GUTIERREZ
Hydrant and Access approval Cleared 6/10/2022 KURT CORRAL
Construction within easement Cleared 7/9/2022 PATRICK MAGALLANES

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/20/2022 Partial Approval PETER FOLLING
Sewer 10/20/2022 Corrections Issued PETER FOLLING
Deputy Drilled-In Anchors 10/26/2022 No Access for Inspection PETER FOLLING
Footing/Foundation/Slab 10/26/2022 Approved PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 11/30/2022 Approved PETER FOLLING
ELECTRICAL-Rough 12/16/2022 Approved PETER FOLLING
HVAC-Rough 12/16/2022 Approved PETER FOLLING
Interior/Exterior Lathing 12/16/2022 Partial Approval JESUS PINEDA
BUILDING-Rough-Frame 1/11/2023 Approved PETER FOLLING
Green Building Rough 1/11/2023 Approved PETER FOLLING
PLUMBING-Rough 1/11/2023 Approved PETER FOLLING
Insulation 1/18/2023 Approved PETER FOLLING
Shower Pan 1/18/2023 Approved PETER FOLLING
Drywall Nailing 1/23/2023 Approved PETER FOLLING
Interior/Exterior Lathing 1/23/2023 Approved PETER FOLLING
ELECTRICAL-Final 3/21/2023 Not Ready for Inspection PETER FOLLING
Final 3/21/2023 Corrections Issued PETER FOLLING
Green Building Final 3/21/2023 Approved PETER FOLLING
HVAC-Final 3/21/2023 Approved PETER FOLLING
PLUMBING-Final 3/21/2023 Approved PETER FOLLING
SGSOV-Seismic Gas S/O Valve 3/21/2023 SGSOV Not Ready PETER FOLLING
Service/Power Release 3/21/2023 Not Ready for Inspection PETER FOLLING
Smoke Detectors 3/21/2023 Approved PETER FOLLING
ELECTRICAL-Final 3/28/2023 Approved PETER FOLLING
ELECTRICAL-Rough 3/28/2023 Approved PETER FOLLING
Final 3/28/2023 OK to Issue CofO PETER FOLLING
HVAC-Final 3/28/2023 Approved PETER FOLLING
PLUMBING-Final 3/28/2023 Approved PETER FOLLING
SGSOV-Seismic Gas S/O Valve 3/28/2023 SGSOV Approved PETER FOLLING