13463 W CHANDLER BLVD 91401
Certificate Information: 13463 W CHANDLER BLVD 91401
- Application / Permit
- 22014-20000-01653
- Plan Check / Job No.
- B22VN05364
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION & MAJOR REMODEL TO (E) 1-STORY SFD (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 10/6/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2022 | NILOOFAR MEHRAIN |
| Corrections Issued | 5/24/2022 | NILOOFAR MEHRAIN |
| Quality Review Completed | 5/26/2022 | STEVEN KIM |
| Building Plans Picked Up | 6/2/2022 | APPLICANT |
| Applicant returned to address corrections | 9/21/2022 | NILOOFAR MEHRAIN |
| Plan Check Approved | 9/27/2022 | NILOOFAR MEHRAIN |
| Issued | 10/6/2022 | APPLICANT |
| CofO in Progress | 9/27/2023 | RYAN SALAZAR |
| CofO Issued | 11/14/2023 | RUBEN SALAS |
| Permit Finaled | 11/14/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/6/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/6/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 9/7/2022 | JULIAN SUNG |
| Roof/Waste drainage to street | Cleared | 9/7/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/14/2022 | Approved | RYAN SALAZAR |
| Deputy Reinf. Concrete | 12/15/2022 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2022 | Partial Approval | JOHN COLEMAN |
| PLUMBING-Rough | 12/23/2022 | Partial Approval | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2022 | Partial Approval | RYAN SALAZAR |
| Deputy Steel/Welding | 1/9/2023 | Conditional Approval | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2023 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2023 | Approved | RYAN SALAZAR |
| HVAC-Rough | 2/1/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 2/1/2023 | Partial Approval | RYAN SALAZAR |
| Gas Test | 2/6/2023 | Approved | JOHN COLEMAN |
| PLUMBING-Rough | 2/6/2023 | Approved | JOHN COLEMAN |
| ELECTRICAL-Rough | 2/9/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Pool Piping | 2/9/2023 | Not Ready for Inspection | RYAN SALAZAR |
| ELECTRICAL-Rough | 2/13/2023 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 2/15/2023 | Approved | THOMAS FINNILA |
| Shower Pan | 2/16/2023 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 2/17/2023 | Approved | WILLIAM WREN |
| Insulation | 2/17/2023 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 2/21/2023 | Corrections Issued | THOMAS FINNILA |
| Drywall Nailing | 2/24/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 2/24/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 2/28/2023 | Approved | RYAN SALAZAR |
| Special/Order Compliance | 5/3/2023 | Partial Inspection | RYAN SALAZAR |
| BUILDING-Rough-Frame | 8/28/2023 | Approved | RYAN SALAZAR |
| Final | 8/28/2023 | Corrections Issued | RYAN SALAZAR |
| Green Building Final | 8/28/2023 | Approved | RYAN SALAZAR |
| Green Building Rough | 8/28/2023 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 8/28/2023 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 8/28/2023 | Approved | RYAN SALAZAR |
| Final | 9/5/2023 | Partial Approval | RYAN SALAZAR |
| Final | 9/27/2023 | OK to Issue CofO | RYAN SALAZAR |