7814 N STANSBURY AVE 91402
Certificate Information: 7814 N STANSBURY AVE 91402
- Application / Permit
- 22014-20000-01652
- Plan Check / Job No.
- B22VN05355
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (28'-7"x22'-1"), 1133 SQFT ADDITION OF A 2-STORY ADU ATTACHED TO THE EXISTING (E) DET. GARAGE, PER LAMC 12.22 A.33(c)(d) “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the finaling of the permit.”
- Permit Issued
- Issued on 9/23/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/12/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2022 | PETER MOSESIAN |
| Corrections Issued | 5/11/2022 | PETER MOSESIAN |
| Quality Review Completed | 5/23/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 5/23/2022 | APPLICANT |
| Plan Check Approved | 9/23/2022 | PETER MOSESIAN |
| Issued | 9/23/2022 | APPLICANT |
| CofO in Progress | 4/6/2023 | GREGG CUMMINGS |
| CofO Issued | 4/12/2023 | MICHAEL SMITH |
| Permit Finaled | 4/12/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 6/1/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/2/2022 | ROMAN GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 6/2/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 6/2/2022 | ROMAN GUTIERREZ |
| Public Works-Highway Ded. | Cleared | 6/2/2022 | ROMAN GUTIERREZ |
| Public Works-Open Permits | Cleared | 6/2/2022 | ROMAN GUTIERREZ |
| Public Works-Sewers | Cleared | 6/2/2022 | ROMAN GUTIERREZ |
| Construction near power lines | Cleared | 9/21/2022 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/6/2022 | Partial Approval | WILLIAM WREN |
| Deputy Drilled-In Anchors | 10/13/2022 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 10/13/2022 | Approved | WILLIAM WREN |
| Footing/Foundation/Slab | 10/13/2022 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2022 | Partial Approval | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2022 | Corrections Issued | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2022 | Partial Approval | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2022 | Corrections Issued | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2022 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 11/9/2022 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 11/9/2022 | Approved | GREGG CUMMINGS |
| Green Building Rough | 11/9/2022 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 11/9/2022 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 11/9/2022 | Approved | GREGG CUMMINGS |
| Insulation | 11/16/2022 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 11/16/2022 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 11/21/2022 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 11/21/2022 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 11/21/2022 | Corrections Issued | GREGG CUMMINGS |
| Shower Pan | 11/30/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Sewer | 12/6/2022 | Approved | MATTHEW NELSON |
| Shower Pan | 12/6/2022 | Approved | MATTHEW NELSON |
| Underground Mechanical | 12/6/2022 | Approved | MATTHEW NELSON |
| Final | 2/16/2023 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 2/16/2023 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 2/16/2023 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 2/16/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 2/28/2023 | Corrections Issued | GREGG CUMMINGS |
| Smoke Detectors | 2/28/2023 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 4/5/2023 | Approved | GREGG CUMMINGS |
| Final | 4/5/2023 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 4/5/2023 | Order to Comply Issued | GREGG CUMMINGS |
| PLUMBING-Final | 4/5/2023 | Approved | GREGG CUMMINGS |