13426 W BLYTHE ST 91402

Certificate Information: 13426 W BLYTHE ST 91402

Application / Permit
22014-20000-01624
Plan Check / Job No.
B22VN05324
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
DEMO (E) PATIO COVER FOR 33' X 14'-4" ADDITION TO (E) SFD.
Permit Issued
Issued on 8/30/2022
Issuing Office
Valley
Current Status
Issued on 8/30/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/11/2022 APPLICANT
Assigned to Plan Check Engineer 4/13/2022 LUIS RINCON
Corrections Issued 4/16/2022 LUIS RINCON
Plan Check Approved 8/30/2022 SERGIO MUNIZ
Issued 8/30/2022 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/19/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 4/26/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 4/26/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor M L Builders And Design; Lic. No.: 953612-B 10400 GLORIA AVENUE      GRANADA HILLS, CA 91344
Engineer Ramos,, Pablo De La Cruz; Lic. No.: S6905 5119 W 129TH      HAWTHORNE, CA 90250

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/31/2022 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 9/1/2022 Corrections Issued ALAN MORELOS
PLUMBING-Rough 9/1/2022 Corrections Issued ALAN MORELOS
Footing/Foundation/Slab 9/7/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Rough 9/7/2022 Partial Approval CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 9/8/2022 Corrections Issued CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 9/19/2022 Corrections Issued GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 9/19/2022 Approved GREGG CUMMINGS
Footing/Foundation/Slab 9/19/2022 Approved GREGG CUMMINGS
Wood Frame 9/22/2022 Off-Hour Fees Due
Wood Frame 9/22/2022 Partial Inspection GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 9/27/2022 Partial Approval GREGG CUMMINGS
BUILDING-Rough-Frame 10/31/2022 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 10/31/2022 Corrections Issued GREGG CUMMINGS
Green Building Rough 10/31/2022 Not Ready for Inspection GREGG CUMMINGS
HVAC-Rough 10/31/2022 Corrections Issued GREGG CUMMINGS
Interior/Exterior Lathing 10/31/2022 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 10/31/2022 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 11/7/2022 Approved GREGG CUMMINGS
ELECTRICAL-Rough 11/7/2022 Approved GREGG CUMMINGS
Green Building Rough 11/7/2022 Approved GREGG CUMMINGS
HVAC-Rough 11/7/2022 Approved GREGG CUMMINGS
Interior/Exterior Lathing 11/7/2022 Not Ready for Inspection GREGG CUMMINGS
Special/Order Compliance 11/7/2022 Corrections Issued GREGG CUMMINGS
Insulation 11/18/2022 Approved GREGG CUMMINGS
Shower Pan 11/18/2022 Approved GREGG CUMMINGS
Drywall Nailing 12/2/2022 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 12/2/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 8/14/2023 Not Ready for Inspection GREGG CUMMINGS
Final 8/14/2023 Corrections Issued GREGG CUMMINGS
Green Building Final 8/14/2023 Not Ready for Inspection GREGG CUMMINGS
HVAC-Final 8/14/2023 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Final 8/14/2023 Not Ready for Inspection GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 8/14/2023 SGSOV Not Ready GREGG CUMMINGS
Smoke Detectors 8/14/2023 Not Ready for Inspection GREGG CUMMINGS
Final 10/27/2023 Corrections Issued GREGG CUMMINGS
Green Building Final 10/27/2023 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 10/27/2023 SGSOV Approved GREGG CUMMINGS
Smoke Detectors 10/27/2023 Approved GREGG CUMMINGS